Ampang/Sri Petaling LRT Line Repair Completion Delayed Till February 2024
-full_normal.jpg)
Rapid Rail Sdn Bhd (Rapid Rail), the operator of the Ampang/Sri Petaling LRT Line, announced that the comprehensive repair work (Phase 2) on the viaduct structure and tracks near the Bandaraya LRT Station is delayed and is expected to be completed, and normal operations resume on 29 February 2024.
The original plan for completing the repair work and restoring normal operations on this route was in mid-October 2023. However, the additional time is necessary because, in addition to the initial damage to viaduct 163, several other damages have been identified on nearby viaduct structures, namely viaducts 164 and 165, which require thorough repairs.
-full_normal.jpg)
After consulting with engineering experts, additional work is required on these viaduct structures to ensure they are safe, meet specifications, and can fulfil the criteria for normal safe operations.
These repair works also involve consultation, assessment, and approval from the Department of Irrigation and Drainage (JPS) of the Federal Territories, as support structures need to be installed along the Klang River adjacent to the affected LRT viaducts.
-full_normal.jpg)
Safety considerations are a top priority for all parties involved in carrying out these high-risk tasks and this additional work has extended the timeline for the restoration work by 3 months.
Rapid Rail is extending its apologies for the inconvenience experienced by commuters. The decision to extend the timeline for the restoration work is to ensure that all damages are identified and repaired to guarantee the safety of public transportation operations and users.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRM7953
SELANGOR
BST2774
JOHOR
JD2291J
PULAU PINANG
PSF1426
PERAK
APL348
PAHANG
CFH5564
KEDAH
KGH7466
NEGERI SEMBILAN
NEL5896
KOTA KINABALU
SJT7323
KUCHING
QAB4602P
Last updated 27 Aug, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Sri Petaling LRT Line Will Resume Operations On 29 February
Repairs to specific stations along the Sri Petaling LRT line will be completed by the end of February 2024, says Rapid KL.
07-01-2024
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months
Ampang/Sri Petaling LRT repair work would take up to seven months to complete.
22-02-2023
LRT Ampang, Sri Petaling Line Will Get Women’s Coach From Dec 31
RapidKL has announced the implementation of women-only coaches on the LRT Ampang/Sri Petaling line, which will begin on December 31, 2024.
24-12-2024
Direct Service From Ampang, Putra Heights LRT Stations To Masjid Jamek Resumes
LRT passengers from the Ampang and Putra Heights lines can continue their journey to Masjid Jamek effective today.
01-02-2024
Park N Ride Facilities At Ampang & Gombak LRT Station Now Uses ‘Pay & Go App’ Parking Payment
RapidKL announced Park & Ride facilities at Ampang and Gombak LRT Station will now utilise an automatic number plate recognition (ANPR) system.
04-04-2023
Bandaraya-Masjid Jamek LRT Line Closed For Two Weeks - Loke
Ampang LRT line will be closed between the Bandaraya and Masjid Jamek stations for about two weeks.
02-02-2023
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months
Ampang/Sri Petaling LRT repair work would take up to seven months to complete.
22-02-2023
Rapid Rail To Install Temporary LRT Platform Barriers Starting Year-End
Rapid Rail will install temporary platform barriers along key LRT lines starting the end of this year.
17-10-2025
Latest News
Perodua's Supplier Just Dropped A Huge RM54Mil Clue About A Secret New Model Launching In 2027
Perodua supplier MCE Holdings drops an RM54M clue about a secret 2027 model. Read about the upcoming next-gen Myvi, Bezza facelift, and local ADAS tech.
27-08-2026
Proton Almost Built A RM150,000 Mid-Engined Sports Car Using Lotus Tech & Wira Parts
Did you know Proton almost built a RM150k mid-engined sports car? Discover how 'Project Sepang' combined Lotus engineering, Wira parts, and Petronas tech.
26-08-2026
RM1,000 Trade-In Subsidy For Old Motorcycles: Transport Ministry Considers New Scheme
Got an old motor? MOT is considering a RM1,000 trade-in subsidy to help Malaysian riders upgrade to new CKD bikes. Here is how the proposed scheme works.
26-08-2026
Do You REALLY Have To Give Way To Every Siren? What Experts Say About VIP Convoys vs. Emergencies
Do you legally have to give way to VIP convoys in Malaysia? Here is what traffic laws and safety experts say about sirens, outriders, and RM10k fines.
26-08-2026
"Can I Pass My Diesel Quota To My Family?" — 3 Big Changes Coming To Malaysia’s Diesel Subsidy System
KPDN & MOF to launch 3 diesel subsidy updates in less than a month, covering family quota transfers, sambung bayar eligibility, and easier applications.
24-08-2026
Hannah Yeoh & Amirudin Shari Unveil 5 Emergency Steps To Fix Klang Valley Floods Before Budget 2027
Hannah Yeoh & Amirudin Shari unveil a 5-step Klang Valley flood mitigation plan covering dam reviews, retention ponds, and river desilting before Budget 2027.
24-08-2026
Mat Rempit Shut Down Linkedua Highway Near JPO So They Could Race — Grown Men Aged Up To 45 Arrested
PDRM arrests 8 men aged 26 to 45 after a viral video over the weekend showed street racers shutting down the Linkedua Highway near JPO in Johor for a race.
24-08-2026
Cycle & Carriage Sells Its Malaysia & Singapore Business To Indonesian Billionaire For RM868 Million
Jardine Cycle & Carriage sells its Malaysia & Singapore car business for RM868 million to Indonesia's Chandra Asri. Here is what it means for car owners!
21-08-2026
Show More
trending_flat