Ampang/Sri Petaling LRT Line Repair Completion Delayed Till February 2024
-full_normal.jpg)
Rapid Rail Sdn Bhd (Rapid Rail), the operator of the Ampang/Sri Petaling LRT Line, announced that the comprehensive repair work (Phase 2) on the viaduct structure and tracks near the Bandaraya LRT Station is delayed and is expected to be completed, and normal operations resume on 29 February 2024.
The original plan for completing the repair work and restoring normal operations on this route was in mid-October 2023. However, the additional time is necessary because, in addition to the initial damage to viaduct 163, several other damages have been identified on nearby viaduct structures, namely viaducts 164 and 165, which require thorough repairs.
-full_normal.jpg)
After consulting with engineering experts, additional work is required on these viaduct structures to ensure they are safe, meet specifications, and can fulfil the criteria for normal safe operations.
These repair works also involve consultation, assessment, and approval from the Department of Irrigation and Drainage (JPS) of the Federal Territories, as support structures need to be installed along the Klang River adjacent to the affected LRT viaducts.
-full_normal.jpg)
Safety considerations are a top priority for all parties involved in carrying out these high-risk tasks and this additional work has extended the timeline for the restoration work by 3 months.
Rapid Rail is extending its apologies for the inconvenience experienced by commuters. The decision to extend the timeline for the restoration work is to ensure that all damages are identified and repaired to guarantee the safety of public transportation operations and users.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRA2444
SELANGOR
BSQ3640
JOHOR
JYX3040
PULAU PINANG
PSC5019
PERAK
APH6757
PAHANG
CFG6020
KEDAH
KGG2171
NEGERI SEMBILAN
NEK4872
KOTA KINABALU
SJR9999*
KUCHING
QAB8428N
Last updated 27 May, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Sri Petaling LRT Line Will Resume Operations On 29 February
Repairs to specific stations along the Sri Petaling LRT line will be completed by the end of February 2024, says Rapid KL.
07-01-2024
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months
Ampang/Sri Petaling LRT repair work would take up to seven months to complete.
22-02-2023
LRT Ampang, Sri Petaling Line Will Get Women’s Coach From Dec 31
RapidKL has announced the implementation of women-only coaches on the LRT Ampang/Sri Petaling line, which will begin on December 31, 2024.
24-12-2024
Direct Service From Ampang, Putra Heights LRT Stations To Masjid Jamek Resumes
LRT passengers from the Ampang and Putra Heights lines can continue their journey to Masjid Jamek effective today.
01-02-2024
Park N Ride Facilities At Ampang & Gombak LRT Station Now Uses ‘Pay & Go App’ Parking Payment
RapidKL announced Park & Ride facilities at Ampang and Gombak LRT Station will now utilise an automatic number plate recognition (ANPR) system.
04-04-2023
Bandaraya-Masjid Jamek LRT Line Closed For Two Weeks - Loke
Ampang LRT line will be closed between the Bandaraya and Masjid Jamek stations for about two weeks.
02-02-2023
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months
Ampang/Sri Petaling LRT repair work would take up to seven months to complete.
22-02-2023
Rapid Rail To Install Temporary LRT Platform Barriers Starting Year-End
Rapid Rail will install temporary platform barriers along key LRT lines starting the end of this year.
17-10-2025
Latest News
3,500+ Proton Drivers Choose ChargeSini for Home Installation, Here’s Why
Buying a Proton e.MAS? Discover why 3,500+ drivers choose ChargeSini for home EV charger installation. Get a 10% public promo!
26-05-2026
Genting "Toll" Starts May 28, But Here Is Why Malaysian Bikers Are Celebrating The New Rules
Lingkaran Cekap Sdn Bhd introduces a new RM5 road charge for cars entering Jalan Genting Highlands starting May 28, 2026, while motorcycles receive full exemption.
26-05-2026
JPJ Terengganu Calls Out Young Riders Over Alarming Rise In Riding Unlicensed & Helmetless
Terengganu JPJ Director Mohd Zamri Samion calls out the casual attitude (sikap sambil lewa) of young motorcyclists riding unlicensed and helmetless.
26-05-2026
Anthony Loke Forces Vulnerable JPJ Systems Back Online Despite Active Fraud Exposure
Transport Minister Anthony Loke instructs JPJ to postpone its online vehicle transfer system upgrade to the long weekend, keeping the system active despite major fraud warnings.
25-05-2026
The End of Crazy Price Drops: A Market Analyst Says EV Pricing Is Finally Becoming "Rational" In Malaysia
A CIMB Securities automotive analyst reveals why MITI’s new July 1 CBU EV policy will end aggressive price wars and push imported EV showroom prices past RM300k.
25-05-2026
10 BIG Reasons To Visit KLIMS 2026 Even If You’re Not A Car Enthusiast
Discover 10 massive reasons to visit KLIMS 2026 at MITEC from June 12–21, featuring free weekday entry, live RIUH concerts, a Pokémon truck, simulators, and smart transit options.
21-05-2026
Game Over, Tonto! JPJ Teams Up With MACC To Hunt Down Secret Lorry Informant Syndicates
JPJ partners with the MACC to dismantle a secret "tonto" sticker syndicate helping heavy commercial lorries evade law enforcement checkpoints.
21-05-2026
254,000 Cars Sold So Far In 2026! A Look At Which Malaysian States Are Freezing In Traffic
Over 254,000 new cars have hit Malaysian roads in the first 4 months of 2026. Discover how MAA’s April sales surged 17% as vehicle production ramped up post-Raya.
20-05-2026
Show More
trending_flat