Ampang/Sri Petaling LRT Line Repair Completion Delayed Till February 2024
-full_normal.jpg)
Rapid Rail Sdn Bhd (Rapid Rail), the operator of the Ampang/Sri Petaling LRT Line, announced that the comprehensive repair work (Phase 2) on the viaduct structure and tracks near the Bandaraya LRT Station is delayed and is expected to be completed, and normal operations resume on 29 February 2024.
The original plan for completing the repair work and restoring normal operations on this route was in mid-October 2023. However, the additional time is necessary because, in addition to the initial damage to viaduct 163, several other damages have been identified on nearby viaduct structures, namely viaducts 164 and 165, which require thorough repairs.
-full_normal.jpg)
After consulting with engineering experts, additional work is required on these viaduct structures to ensure they are safe, meet specifications, and can fulfil the criteria for normal safe operations.
These repair works also involve consultation, assessment, and approval from the Department of Irrigation and Drainage (JPS) of the Federal Territories, as support structures need to be installed along the Klang River adjacent to the affected LRT viaducts.
-full_normal.jpg)
Safety considerations are a top priority for all parties involved in carrying out these high-risk tasks and this additional work has extended the timeline for the restoration work by 3 months.
Rapid Rail is extending its apologies for the inconvenience experienced by commuters. The decision to extend the timeline for the restoration work is to ensure that all damages are identified and repaired to guarantee the safety of public transportation operations and users.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VSB5098
SELANGOR
BSV4475
JOHOR
JJ4597J
PULAU PINANG
PSH7347
PERAK
APN3853
PAHANG
CFJ5224
KEDAH
KGK1051
NEGERI SEMBILAN
NEM7520
KOTA KINABALU
SJV4346
KUCHING
QAB1580Q
Last updated 28 Nov, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Sri Petaling LRT Line Will Resume Operations On 29 February
Repairs to specific stations along the Sri Petaling LRT line will be completed by the end of February 2024, says Rapid KL.
07-01-2024
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months
Ampang/Sri Petaling LRT repair work would take up to seven months to complete.
22-02-2023
LRT Ampang, Sri Petaling Line Will Get Women’s Coach From Dec 31
RapidKL has announced the implementation of women-only coaches on the LRT Ampang/Sri Petaling line, which will begin on December 31, 2024.
24-12-2024
Direct Service From Ampang, Putra Heights LRT Stations To Masjid Jamek Resumes
LRT passengers from the Ampang and Putra Heights lines can continue their journey to Masjid Jamek effective today.
01-02-2024
Park N Ride Facilities At Ampang & Gombak LRT Station Now Uses ‘Pay & Go App’ Parking Payment
RapidKL announced Park & Ride facilities at Ampang and Gombak LRT Station will now utilise an automatic number plate recognition (ANPR) system.
04-04-2023
Bandaraya-Masjid Jamek LRT Line Closed For Two Weeks - Loke
Ampang LRT line will be closed between the Bandaraya and Masjid Jamek stations for about two weeks.
02-02-2023
Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months
Ampang/Sri Petaling LRT repair work would take up to seven months to complete.
22-02-2023
Rapid Rail To Install Temporary LRT Platform Barriers Starting Year-End
Rapid Rail will install temporary platform barriers along key LRT lines starting the end of this year.
17-10-2025
Latest News
XPENG Malaysia After Bermaz: Warranty, Servicing And Ownership Guide
Own an XPENG in Malaysia? Find out what happens to your warranty, free maintenance, service centres and existing bookings after Bermaz's exit.
27-11-2026
Malaysia Car Sales Forecast 2026: CIMB Sees 815,000 Units
Malaysia car sales could reach 815,000 units in 2026, says CIMB. But aggressive discounts may squeeze automakers' profit margins.
26-11-2026
Proton Persona Ends 19-Year Production Run, Final Car Delivered
Proton delivers the final Persona after 19 years and 473,346 sales. Explore its history, final handover and the S70 replacing it in Malaysia.
25-11-2026
JETOUR T2 Appears In Takluk 2: Op Daulat Movie
JETOUR T2 appears in Takluk 2: Op Daulat, opening 26 November. Here's what Carz spotted at the premiere and how JETOUR is involved.
25-11-2026
Federal Highway Jams: Govt Reviews New Toll Highway Proposals
The govt is reviewing new toll highway proposals to ease Federal Highway jams. Here's why widening isn't planned and what motorists should know.
25-11-2026
JPJ Requires Updated Address, Email And Phone Number Details
JPJ requires updated address, email and phone details. Here's what Malaysians need to check, how to update their information and what JPJ says about deadlines.
24-11-2026
Penang ANPR: 27,734 Parking Fines Cancelled, Future Plans Explained
Penang has no plans to resume ANPR parking enforcement after cancelling 27,734 fines and refunding RM203,170. Here's what drivers should know.
23-11-2026
Yangwang U9 And U8 To Be Displayed In Malaysia At MATRADE, Nov 27–29
The Yangwang U9 and U8 are coming to Malaysia for a special showcase at MATRADE from Nov 27–29. Here's where to see them and what makes them special.
23-11-2026
Show More
trending_flat
Malaysia First Used Car and EV Consignment Platform
This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

Understanding CariCarzAutomall Consignment Plan


Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge