Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway

The construction of Phase 1A of the Pan Borneo Highway (LPB) in Sabah is taking longer than anticipated, as stated by Deputy Works Minister, Datuk Seri Ahmad Maslan. Difficult land acquisition circumstances and the drawn-out utility relocation process are to blame for these delays.
He emphasized that the landowners' resistance to cooperate has caused delays and the need for an extension of time, with some even going so far as to file a lawsuit, according to Bernama.
As of August 2024, 79.48% of the 15 work packages in Phase 1A had been completed. “Four work packages have been completed and are now open to road users, while the remaining packages are at various stages of construction. These are expected to be finished in phases by the first quarter of 2026. Phase 1A covers an estimated distance of 283 km,” said Ahmad Maslan.

“In addition, I hope the construction team can complete this project by meeting the quality, cost, and time standards set forth, in line with the MY Jalan KK programme’s goal of delivering comfortable and safe infrastructure for all Malaysia Madani people,” he added.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRU7184
SELANGOR
BSU5201
JOHOR
JG1465J
PULAU PINANG
PSG6018
PERAK
APM3984
PAHANG
CFJ1773
KEDAH
KGJ5296
NEGERI SEMBILAN
NEM3489
KOTA KINABALU
SJU6323
KUCHING
QAB7901P
Last updated 21 Oct, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah
PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.
06-08-2024
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target
Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.
26-06-2024
Pan Borneo highway status in Sabah and Sarawak
The condition of the Pan Borneo Highway in Sabah and Sarawak
06-12-2022
Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year
Work on the 4.95km Miri Section will move from planning to physical construction in the first quarter of 2026.
04-12-2025
Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah
PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.
06-08-2024
Pan Borneo Highway Project Will Be Completed This Year - Nanta
98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed, says the works minister.
13-02-2024
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target
Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.
26-06-2024
Latest News
Proton's Exports Are Growing, But Not All The Cars Wear Proton Badges
Proton exported 7,370 vehicles in the first nine months of 2026, including Geely cars built in Malaysia. Here's why it matters for Tanjong Malim.
21-10-2026
6,537 Road Deaths In 2025 - Can Malaysia's New Safety Push Make A Difference?
Malaysia recorded 6,537 road deaths in 2025. With a new MOT-MIROS proposal underway, can the country meet its target to halve fatalities by 2030?
20-10-2026
ECRL Vs Driving To Kota Bharu: Petrol, EV Or Train, Which Costs Less?
ECRL fares to Kota Bharu start at RM125. We compare train tickets with petrol and EV energy costs to see which option makes more sense.
19-10-2026
"We'd Love To Go Back": Mercedes Eyes Sepang Return As F1 Night Race Idea Emerges
Mercedes-AMG Petronas F1 wants to return to Sepang, while Signify says a night race is technically possible. Could Malaysia's next F1 race be after dark?
19-10-2026
RM52,000 In Car Rebates? Sime Motors' 3-Day Sale Is Now On!
Sime Motors' 3-day sale runs from 16 to 18 October 2026 in Ara Damansara, with car rebates up to RM52,000, test drives and special offers.
16-10-2026
RM950 Million From F1 At Sepang. So Why Is Malaysia Still Hesitating?
F1 at Sepang generated nearly RM950 million in economic impact. But a five-year Malaysian GP deal could cost RM1.5 billion. Here's why.
16-10-2026
35 Cars Daily! BYD's New Miri 3S Centre Puts Aftersales In Focus
BYD's new Miri 3S Centre can service up to 35 cars daily. Here's how the latest Sarawak expansion strengthens aftersales support for EV owners.
15-10-2026
Chery Omoda 5 Recall: 600 Cars In 2024, 8,878 In 2026. What Changed?
Chery's Omoda 5 recall covers 8,878 vehicles, compared with 600 in 2024. Here's what changed, what remains unknown and what owners should do.
15-10-2026
Show More
trending_flat
Malaysia First Used Car and EV Consignment Platform
This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

Understanding CariCarzAutomall Consignment Plan


Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge