Kelana Jaya Line Signalling Works Delayed, Phase 2 Work Starts Sept 6

The planned upgrade works for Phases 2 and 3 of the Kelana Jaya Line signalling system, originally set to begin on Aug 9, have been postponed to Sept 6.
Prasarana Malaysia Berhad announced recently the delay is to allow more time for testing the newly installed Phase 1 signalling system. The additional tests are essential to evaluate the system's performance in real-world conditions and to reduce the chances of future disruptions.
For Phase 1, the upgrades were done during overnight maintenance hours as the works were confined to depot areas and did not impact the main train service. The entire project is part of a broader effort to strengthen the system following a major disruption in Nov 2022.
-full_normal.jpg)
With the revised schedule, Phase 2 works will now take place on selected days in September and October, affecting the KLCC to Gombak stretch. Phase 3 will follow in November, covering stations from Lembah Subang to Ampang Park.
On those specific dates, trains at affected stations will begin operating later than usual, only opening to passengers from 9AM instead of the normal 6AM start. Services at all other stations will run as scheduled.

To ease passenger travel during these disruptions, free shuttle buses and vans will be available between the affected stations.
The new SelTrac Generation 8 system being installed offers real-time data capabilities, stronger cybersecurity, and more reliable communication. It is expected to extend the current system’s lifespan by as much as 20 years.
More information on affected stations and updates can be found at www.myrapid.com.my
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRM4683
SELANGOR
BST2036
JOHOR
JD589J
PULAU PINANG
PSF532
PERAK
APK9278
PAHANG
CFH5328
KEDAH
KGH7083
NEGERI SEMBILAN
NEL5611
KOTA KINABALU
SJT6741
KUCHING
QAB4464P
Last updated 26 Aug, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Loke Directs Prasarana To Meet On Klang Valley Train Disruptions
Prasarana has been directed by Loke to hold a special meeting to find the source of the technical issues affecting the MRT and LRT lines.
29-03-2023
Prasarana To Spend RM2.8b To Improve Train, Bus Services
A total of RM2.8 billion will be spent by Prasarana to upgrade the train and bus systems.
09-01-2023
Rapid Rail Extends Service At Bukit Jalil Stadium - AFF MITSUBISHI ELECTRIC CUP 2022
Rapid Rail extends operation till 12.30 am (8 Jan) for AFF MITSUBISHI ELECTRIC CUP 2022 at Bukit Jalil National Stadium.
06-01-2023
Kelana Jaya LRT Line Suffers Yet Another Malfunction
RapidKL issued a statement that the delays were caused by a switch malfunctions issue which causes all trains on the line to move slower and stop longer at the platform.
06-01-2023
Rapid On-Demand: 19K Daily Trips, Fare Revised to RM2
Rapid On-Demand has reached 19,000 daily trips, prompting a fare revision to a RM2 beginning Feb 2026.
20-01-2026
Prasarana Moved 1.54 Million People on New Year’s Eve
Prasarana moved 1.54 million people on New Year’s Eve, marking its highest single-day ridership.
02-01-2026
PRIDE, SPX Launch Smart Lockers at Five LRT Stations
PRIDE and SPX Express aim to add convenience for commuters with new automated lockers primed in five LRT stations.
30-09-2025
Rapid Rail Set To Launch Real-Time Crowd Tracking & AI Security
Rapid Rail will introduce a live tracker showing coach crowd levels so commuters can board with less stress.
23-09-2025
Latest News
"Can I Pass My Diesel Quota To My Family?" — 3 Big Changes Coming To Malaysia’s Diesel Subsidy System
KPDN & MOF to launch 3 diesel subsidy updates in less than a month, covering family quota transfers, sambung bayar eligibility, and easier applications.
24-08-2026
Hannah Yeoh & Amirudin Shari Unveil 5 Emergency Steps To Fix Klang Valley Floods Before Budget 2027
Hannah Yeoh & Amirudin Shari unveil a 5-step Klang Valley flood mitigation plan covering dam reviews, retention ponds, and river desilting before Budget 2027.
24-08-2026
Mat Rempit Shut Down Linkedua Highway Near JPO So They Could Race — Grown Men Aged Up To 45 Arrested
PDRM arrests 8 men aged 26 to 45 after a viral video over the weekend showed street racers shutting down the Linkedua Highway near JPO in Johor for a race.
24-08-2026
Cycle & Carriage Sells Its Malaysia & Singapore Business To Indonesian Billionaire For RM868 Million
Jardine Cycle & Carriage sells its Malaysia & Singapore car business for RM868 million to Indonesia's Chandra Asri. Here is what it means for car owners!
21-08-2026
Do Government Vehicles With Sirens Have The Right To Run Red Lights In Malaysia? Here's What Cops Say
Do emergency warning lights give vehicles carte blanche to run red lights in Malaysia? Bukit Aman clarifies traffic laws following a fatal KL crash.
21-08-2026
Immigration Driver Pleads Not Guilty After Running Red Light & Killing Father And Two Daughters
Immigration driver Mohd Akbar Zainol pleads not guilty to 5 charges after running a red light in KL, hitting a car, and killing 3 pedestrians.
20-08-2026
PDRM Is Spending RM8 Million On Silent E-Bikes For Border Patrols: Here’s What They Can Do
PDRM receives 375 silent tactical e-bikes worth RM8M! Discover how the 850Nm torque Jebatt F29 will stop border smuggling.
20-08-2026
Immigration Truck Runs Red Light In KL: Father & 2 Daughters Killed, Mother In Red Zone
3 family members were killed after an Immigration truck ran a red light and crashed at Maju Junction, KL. Get the latest police details and investigation updates.
19-08-2026
Show More
trending_flat