West Coast Expressway On Track For 2027 Completion
The long-awaited West Coast Expressway (WCE) is edging closer to completion, with WCE Holdings Bhd (WHB) targeting 2027 to wrap up the 233km highway linking Banting in Selangor to Taiping in Perak.
Eight of its 11 sections are already open to traffic, and momentum is picking up on the remaining three.
“Section 7 should be done by late 2026, and Section 3 by the first quarter of 2027,” said chief executive officer Lyndon Alfred Felix in a BH report. The expressway is seen as a game changer, easing journeys between Klang, Kuala Selangor, Teluk Intan, Sitiawan and Manjung, while connecting smoothly to other major highways.

Built on flatter ground than traditional routes, it is designed to cut fuel use and make travel safer, especially for heavy vehicles.
Traffic on the open stretches has been promising, boosted by the opening of the Banting–SKVE link last August and the SKVE–Kesas link this January.
“We’re tracking well with our projections. Once the final sections open, traffic should grow even further,” Lyndon stated.
One key hurdle is Section 3, where a land acquisition has yet to be settled. Although compensation was already paid, a single parcel remains occupied.

"Discussions with both state and federal authorities are ongoing," he said, hoping that the matter can be resolved within the next two months.
The company’s numbers are also improving. Toll revenue more than doubled last year to RM125.2 million, helping group revenue climb to RM629.1 million.
In the first quarter of FY26 alone, traffic rose 36% while toll collections surged 61% quarter-on-quarter.

Beyond tolls, WHB is investing in new rest and service areas equipped with EV chargers, renewable energy and greener facilities.
“Our priority now is to complete Sections 3, 4 and 7 that will unlock the full potential of the WCE,” Lyndon concluded.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRA1655
SELANGOR
BSQ3512
JOHOR
JYX2763
PULAU PINANG
PSC4903
PERAK
APH6581
PAHANG
CFG5949
KEDAH
KGG2081
NEGERI SEMBILAN
NEK4832
KOTA KINABALU
SJR9999*
KUCHING
QAB8364N
Last updated 26 May, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
West Coast Expressway Expects 35% Traffic Surge for CNY
WCE anticipates 160,000 vehicles daily during the Chinese New Year festive rush, a 35% increase compared to last year.
14-02-2026
WCE Reports 48% Jump In Toll Revenue, Eyes Full Completion By 2027
Toll collections on the WCE surged 48% in Q2 to RM44.1 million, with the firm aiming for full completion by March 2027.
27-11-2025
Court Upholds Land Takeover For WCE Despite Residents’ Complaint
Judge rules the acquisition for WCE valid even without direct notice, as Kampung Jawa landowners gear up for a crucial valuation hearing.
26-11-2025
Hauliers Warn WCE Delays Hurting Logistics and Economy
The Association of Malaysian Hauliers says delays in completing Section 3 of the WCE are disrupting cargo flow and driving up costs.
29-09-2025
Hari Raya 2025: Over 140K Vehicles Expected Daily on WCE
Over 140,000 vehicles are expected to use the WCE daily during this upcoming Hari Raya Aidilfitri festive season.
24-03-2025
WCE Sees 83% Increment In Traffic & 128% Increment In Toll Collection
WCE sees increased average daily traffic volume by 83% supported by a boost in toll income by 128%.
29-11-2024
West Coast Expressway (WCE) Section 11 Beruas To Taiping Opens Before Raya
Section 11 of the West Coast Expressway (WCE), which runs from Beruas to Taiping (South), is expected to be operational before Hari Raya.
18-01-2024
Section 11 Of the West Coast Expressway Will Complete By Year End
Section 11 of the West Coast Expressway Section from Beruas-Taiping and four more sections will be operational by the end of this year.
11-07-2023
Latest News
3,500+ Proton Drivers Choose ChargeSini for Home Installation, Here’s Why
Buying a Proton e.MAS? Discover why 3,500+ drivers choose ChargeSini for home EV charger installation. Get a 10% public promo!
26-05-2026
Genting "Toll" Starts May 28, But Here Is Why Malaysian Bikers Are Celebrating The New Rules
Lingkaran Cekap Sdn Bhd introduces a new RM5 road charge for cars entering Jalan Genting Highlands starting May 28, 2026, while motorcycles receive full exemption.
26-05-2026
JPJ Terengganu Calls Out Young Riders Over Alarming Rise In Riding Unlicensed & Helmetless
Terengganu JPJ Director Mohd Zamri Samion calls out the casual attitude (sikap sambil lewa) of young motorcyclists riding unlicensed and helmetless.
26-05-2026
Anthony Loke Forces Vulnerable JPJ Systems Back Online Despite Active Fraud Exposure
Transport Minister Anthony Loke instructs JPJ to postpone its online vehicle transfer system upgrade to the long weekend, keeping the system active despite major fraud warnings.
25-05-2026
The End of Crazy Price Drops: A Market Analyst Says EV Pricing Is Finally Becoming "Rational" In Malaysia
A CIMB Securities automotive analyst reveals why MITI’s new July 1 CBU EV policy will end aggressive price wars and push imported EV showroom prices past RM300k.
25-05-2026
10 BIG Reasons To Visit KLIMS 2026 Even If You’re Not A Car Enthusiast
Discover 10 massive reasons to visit KLIMS 2026 at MITEC from June 12–21, featuring free weekday entry, live RIUH concerts, a Pokémon truck, simulators, and smart transit options.
21-05-2026
Game Over, Tonto! JPJ Teams Up With MACC To Hunt Down Secret Lorry Informant Syndicates
JPJ partners with the MACC to dismantle a secret "tonto" sticker syndicate helping heavy commercial lorries evade law enforcement checkpoints.
21-05-2026
254,000 Cars Sold So Far In 2026! A Look At Which Malaysian States Are Freezing In Traffic
Over 254,000 new cars have hit Malaysian roads in the first 4 months of 2026. Discover how MAA’s April sales surged 17% as vehicle production ramped up post-Raya.
20-05-2026
Show More
trending_flat