ECRL Project Hits 87% Completion by August 2025 – MoT

Mukhlis Azman

Share via

ecrl-genting-.jpgph06-19062024-ecrl_4279690_20240619165601.jpg

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

The East Coast Rail Link (ECRL) project spanning Kelantan, Terengganu, Pahang, and Selangor has recorded an overall completion of 87% as of August this year, said Transport Minister Anthony Loke.

As reported by Bernama, the minister said the project segment in Terengganu is among the fastest to be completed, as land issues were resolved earlier, coupled with its overall flat geographical terrain, thus possessing fewer construction challenges.

548195012_1374359560713294_6709422170773546027_n.jpg

Transport Minister YB Anthony Loke

“In Terengganu, track works are almost completed. The only sections yet to be finished are from Bentong to Gombak, particularly the Genting tunnel up to Gombak, which is the most challenging segment,” Loke told reporters after officiating the BAS.MY Kuala Terengganu Service Transformation Programme yesterday.

ECRL_PASIR_PUTEH_1755593670.jpgECRL_Paka_tunnel7_09042021.jpg

That said, the minister continued that progress in both Kelantan and Terengganu remains on track, as most of the major construction works there have been completed. However, he revealed that incidents of cable theft in Pahang have disrupted the work progress in the state.

“More than a kilometre of cables was stolen, which created problems for the developer. They now have to review their approach to accelerate progress.

“I have already discussed this with the Home Ministry and the police. More aggressive action is needed, including enforcing stricter laws to curb this issue,” Loke added.

Apart from causing delays and heavy losses, the minister also pointed out that cable thefts pose high risks to public safety.

ECRL-Map.jpg

Back to the ECRL project, the first phase from Kota Bharu to Gombak is scheduled for completion in December 2026, with first testing and certification set to take place earlier in June 2026. Meanwhile, the second phase, from Gombak to Port Klang, is scheduled to be completed later in December 2027, with the full operations expected to begin in Jan 2028.

Source: Bernama


Gallery

Share This Article

Written By

Mukhlis Azman

An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman

Share via

JPJ Running Numbers

KUALA LUMPUR

VQT2420

SELANGOR

BSP108

JOHOR

JYU4311

PULAU PINANG

PSB2687

PERAK

APG4941

PAHANG

CFG1524

KEDAH

KGF1925

NEGERI SEMBILAN

NEJ9813

KOTA KINABALU

SJR2795

KUCHING

QAB5250N

Last updated 11 Apr, 2026

Fuel Price

Petrol

RON 95

RM 2.59

+0.05

RON 97

RM 3.15

+0.05

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.04

+0.05

EURO 5 B7

RM 3.24

+0.05

Last updated 26 Feb, 2026

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023

Latest News

Auto News
A Sense of Crisis: What Toyota, Ford, and Honda’s Leadership are Saying About the Future

A Sense of Crisis: What Toyota, Ford, and Honda’s Leadership are Saying About the Future

Legacy automakers are facing a 'Change or Die' moment. From Honda's $15.8 billion loss to Toyota's survival warning, see why 'China Speed' is winning.

11-04-2026
Auto News
Why Is Global Oil Falling But Our Petrol Price Is Still High? — MOF Explains The 'Lag'

Why Is Global Oil Falling But Our Petrol Price Is Still High? — MOF Explains The 'Lag'

Why is global oil falling but Malaysia’s petrol price is still high? MOF explains the APM "lag effect" and why unsubsidized RON95 hit RM4.27 this week.

10-04-2026
Auto News
Proton X50 ‘Black Edition' Look Goes Permanent: Quartz Black Now Available for All Variants
Auto News
SUPER GT 2026 Malaysia Might Not Happen At All? Here’s What We Know So Far

SUPER GT 2026 Malaysia Might Not Happen At All? Here’s What We Know So Far

Is SUPER GT 2026 Malaysia cancelled? Reports suggest the Malaysian round may be called off due to fuel concerns and high costs. Get the latest updates here.

07-04-2026
Auto News
Is It Illegal To Borrow Your Parents' MyKad For Subsidised Petrol? Here’s What The Law Says

Is It Illegal To Borrow Your Parents' MyKad For Subsidised Petrol? Here’s What The Law Says

Can you use a family member's MyKad for Budi95 petrol? JPN warns that sharing IDs at the pump is prohibited and under investigation. Get the official rules here.

06-04-2026
Auto News
Tough Times, But Everyone Still Wants a Saga: Sales Jump 38% Despite a Slow Market

Tough Times, But Everyone Still Wants a Saga: Sales Jump 38% Despite a Slow Market

Proton Saga defies the 2026 market slump with a 38% sales surge! Discover the new 1.5L engine, Level 1 ADAS, and tech upgrades making it Malaysia’s top choice.

03-04-2026
Auto News
Malaysia Is Angry… But The World Is Already in Energy Crisis

Malaysia Is Angry… But The World Is Already in Energy Crisis

Malaysia is cutting the BUDI95 quota to 200L. While we argue over liters, the world is in "Energy Survival Mode." Is an EV your secret to beating the 2026 crisis?

03-04-2026
Auto News
GWM Malaysia Eyes Top 10 Spot by 2028: 6 New Models to Launch, Led by Tank 300 HEV

GWM Malaysia Eyes Top 10 Spot by 2028: 6 New Models to Launch, Led by Tank 300 HEV

GWM Malaysia targets Top 10 status by 2028, launching 6 new SUVs starting with the Tank 300 HEV.

02-04-2026

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.