Penang LRT: Major Road Diversions in Bayan Lepas from Jan 2026
-full_normal.jpg)
Major traffic diversions will take place in Bayan Lepas from mid-Jan 2026 as construction of the Penang LRT Mutiara Line gets underway.
According to SRS Consortium project director Adil Putra Ahmad, the first phase will affect Jalan Sultan Azlan Shah between Kampung Jawa and Mayang Pasir. Traffic will be cut from three to two lanes in both directions to allow work on the elevated tracks.
The stretch, over 1KM long, will take about 38 months to complete, with the target set for Dec 2028.
-full_normal.jpg)
-full_normal.jpg)
Traffic control will focus on three main areas: Komtar, Sunny Point and the Free Industrial Zone (FIZ). Adil warned that congestion is unavoidable, while state infrastructure and transport committee chairman Zairil Khir Johari said the state would keep the public updated so drivers can better plan their routes.
He also assured that contractors will follow strict safety measures, especially during the monsoon.
-full_normal.jpg)
The new line will serve key points across the island. Stations are planned at the FIZ, Penang International Airport, Universiti Sains Malaysia, SPICE, and the upcoming Penang Waterfront Convention Centre, with stops through Jelutong, Sungai Pinang and Macallum Street.
A channel crossing will link the island to Penang Sentral, connecting directly to the national rail network.
-full_normal.jpg)
-full_normal.jpg)
“This means someone from Sungai Petani or Padang Besar can take a commuter train to Penang Sentral, transfer to the LRT and continue straight to the airport, USM, Bayan Lepas or Komtar,” Zairil explained.
He described the Mutiara Line as a game-changer, with daily ridership expected to start at 70,000 and grow past 100,000 over time. The system is also expected to cut traffic along the Tun Dr Lim Chong Eu Expressway and surrounding routes.
Source: MalayMail
Gallery
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VSB5098
SELANGOR
BSV4475
JOHOR
JJ4597J
PULAU PINANG
PSH7347
PERAK
APN3853
PAHANG
CFJ5224
KEDAH
KGK1051
NEGERI SEMBILAN
NEM7520
KOTA KINABALU
SJV4346
KUCHING
QAB1580Q
Last updated 28 Nov, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back
Is the 80-minute Penang Bridge crawl finally ending? The Mutiara Line LRT links Butterworth to Komtar in just 8 minutes. Get the latest 2026 project updates, station lists, and more.
17-03-2026
Penang Police Strengthen Security For Mutiara LRT Project
Penang police are coordinating with agencies to ensure the Mutiara LRT project proceeds safely without compromising public security.
18-11-2025
Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment
Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.
14-01-2025
Penang Mutiara Line LRT Project Set to Complete in 2030
The cabinet has approved the construction of the Penang Mutiara Line LRT Project, with completion expected by 2023.
30-03-2024
Anwar: 13MP Pushes for Improved Connectivity – Better Buses, Trains and Roads
The 13th Malaysia Plan focuses on better connectivity through buses, trains, roads, and smarter planning.
31-07-2025
Penang On Track And Well-Prepared For Large Scale Projects
Penang will implement extensive traffic management measures to mitigate disruptions from upcoming large-scale projects.
04-06-2025
Mutiara Line LRT: Penang’s RM8.3 Billion Connectivity Investment
Penang’s RM8.31 billion Mutiara Line LRT project begins with the first phase contract signing.
14-01-2025
Penang Mutiara Line LRT Won’t Be Like Kelana Jaya LRT
Penang’s Mutiara Line LRT would run only 2-car train when it begins and would scale up if required.
31-05-2024
Latest News
XPENG Malaysia After Bermaz: Warranty, Servicing And Ownership Guide
Own an XPENG in Malaysia? Find out what happens to your warranty, free maintenance, service centres and existing bookings after Bermaz's exit.
27-11-2026
Malaysia Car Sales Forecast 2026: CIMB Sees 815,000 Units
Malaysia car sales could reach 815,000 units in 2026, says CIMB. But aggressive discounts may squeeze automakers' profit margins.
26-11-2026
Proton Persona Ends 19-Year Production Run, Final Car Delivered
Proton delivers the final Persona after 19 years and 473,346 sales. Explore its history, final handover and the S70 replacing it in Malaysia.
25-11-2026
JETOUR T2 Appears In Takluk 2: Op Daulat Movie
JETOUR T2 appears in Takluk 2: Op Daulat, opening 26 November. Here's what Carz spotted at the premiere and how JETOUR is involved.
25-11-2026
Federal Highway Jams: Govt Reviews New Toll Highway Proposals
The govt is reviewing new toll highway proposals to ease Federal Highway jams. Here's why widening isn't planned and what motorists should know.
25-11-2026
JPJ Requires Updated Address, Email And Phone Number Details
JPJ requires updated address, email and phone details. Here's what Malaysians need to check, how to update their information and what JPJ says about deadlines.
24-11-2026
Penang ANPR: 27,734 Parking Fines Cancelled, Future Plans Explained
Penang has no plans to resume ANPR parking enforcement after cancelling 27,734 fines and refunding RM203,170. Here's what drivers should know.
23-11-2026
Yangwang U9 And U8 To Be Displayed In Malaysia At MATRADE, Nov 27–29
The Yangwang U9 and U8 are coming to Malaysia for a special showcase at MATRADE from Nov 27–29. Here's where to see them and what makes them special.
23-11-2026
Show More
trending_flat
Malaysia First Used Car and EV Consignment Platform
This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

Understanding CariCarzAutomall Consignment Plan


Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge