Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana Malaysia Bhd has postponed the opening of the Shah Alam LRT Line, emphasising that passenger safety must come first and avoiding any repeat of the 2021 Kelana Jaya LRT collision that injured over 200 passengers.
According to Wan Agyl Wan Hassan, founder and CEO of MY Mobility Vision, the construction work on the line is nearly complete, but the technology running the trains is far more complex.

"The Shah Alam LRT is fully automated (GoA4), meaning the system controls speed, braking, doors, and train spacing entirely via software. Even a minor glitch could cause a train to brake suddenly or disrupt schedules
“Each train must complete a fault-free run (FFR) as required by the Land Public Transport Agency (APAD)
“If a problem occurs, testing must start over. It may not be popular, but it’s necessary to make sure passengers are truly safe," he told The Star.
He added that many countries, including Singapore, the UK, and Australia, have delayed the launch of automated rail lines at the last minute to deal with software integration issues.
-full_normal-(1).jpg)
“In modern rail systems, postponing safety is normal. What’s unusual is opening a system that isn’t fully stable,” Wan Agyl added.
Samirul Ariff Othman, senior consultant at Global Asia Consulting, said extending the testing period is a principled decision, not an unnecessary delay.
“It prioritises system reliability and passenger safety. Rushing the launch could lead to trains stopping mid-track, brake failures, repeated delays, and a damaged public image

"Addressing all issues before operations start prevents costly repairs and long-term negative perception," he noted in the same report.
Source: The star.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRM6421
SELANGOR
BST2457
JOHOR
JD1649J
PULAU PINANG
PSF1146
PERAK
APK9676
PAHANG
CFH5430
KEDAH
KGH7291
NEGERI SEMBILAN
NEL5750
KOTA KINABALU
SJT7035
KUCHING
QAB4551P
Last updated 27 Aug, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Forget Luxury Condos! PM Anwar Wants Affordable Homes Next To Train Stations – Here’s The Plan
PM Anwar wants affordable homes, not luxury condos, next to LRT3 stations! See the 4 locations identified for new Transit-Oriented Developments in the Klang Valley.
30-06-2026
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
LRT3 Shah Alam Line Expected To Open In June
After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.
05-02-2026
Prasarana Ridership Jumps 11% in 2025
Prasarana ridership jumps 11% in 2025 hitting 1.31 million users.
07-01-2026
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
Latest News
Proton Almost Built A RM150,000 Mid-Engined Sports Car Using Lotus Tech & Wira Parts
Did you know Proton almost built a RM150k mid-engined sports car? Discover how 'Project Sepang' combined Lotus engineering, Wira parts, and Petronas tech.
26-08-2026
RM1,000 Trade-In Subsidy For Old Motorcycles: Transport Ministry Considers New Scheme
Got an old motor? MOT is considering a RM1,000 trade-in subsidy to help Malaysian riders upgrade to new CKD bikes. Here is how the proposed scheme works.
26-08-2026
Do You REALLY Have To Give Way To Every Siren? What Experts Say About VIP Convoys vs. Emergencies
Do you legally have to give way to VIP convoys in Malaysia? Here is what traffic laws and safety experts say about sirens, outriders, and RM10k fines.
26-08-2026
"Can I Pass My Diesel Quota To My Family?" — 3 Big Changes Coming To Malaysia’s Diesel Subsidy System
KPDN & MOF to launch 3 diesel subsidy updates in less than a month, covering family quota transfers, sambung bayar eligibility, and easier applications.
24-08-2026
Hannah Yeoh & Amirudin Shari Unveil 5 Emergency Steps To Fix Klang Valley Floods Before Budget 2027
Hannah Yeoh & Amirudin Shari unveil a 5-step Klang Valley flood mitigation plan covering dam reviews, retention ponds, and river desilting before Budget 2027.
24-08-2026
Mat Rempit Shut Down Linkedua Highway Near JPO So They Could Race — Grown Men Aged Up To 45 Arrested
PDRM arrests 8 men aged 26 to 45 after a viral video over the weekend showed street racers shutting down the Linkedua Highway near JPO in Johor for a race.
24-08-2026
Cycle & Carriage Sells Its Malaysia & Singapore Business To Indonesian Billionaire For RM868 Million
Jardine Cycle & Carriage sells its Malaysia & Singapore car business for RM868 million to Indonesia's Chandra Asri. Here is what it means for car owners!
21-08-2026
Do Government Vehicles With Sirens Have The Right To Run Red Lights In Malaysia? Here's What Cops Say
Do emergency warning lights give vehicles carte blanche to run red lights in Malaysia? Bukit Aman clarifies traffic laws following a fatal KL crash.
21-08-2026
Show More
trending_flat