Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana Malaysia Bhd has postponed the opening of the Shah Alam LRT Line, emphasising that passenger safety must come first and avoiding any repeat of the 2021 Kelana Jaya LRT collision that injured over 200 passengers.
According to Wan Agyl Wan Hassan, founder and CEO of MY Mobility Vision, the construction work on the line is nearly complete, but the technology running the trains is far more complex.

"The Shah Alam LRT is fully automated (GoA4), meaning the system controls speed, braking, doors, and train spacing entirely via software. Even a minor glitch could cause a train to brake suddenly or disrupt schedules
“Each train must complete a fault-free run (FFR) as required by the Land Public Transport Agency (APAD)
“If a problem occurs, testing must start over. It may not be popular, but it’s necessary to make sure passengers are truly safe," he told The Star.
He added that many countries, including Singapore, the UK, and Australia, have delayed the launch of automated rail lines at the last minute to deal with software integration issues.
-full_normal-(1).jpg)
“In modern rail systems, postponing safety is normal. What’s unusual is opening a system that isn’t fully stable,” Wan Agyl added.
Samirul Ariff Othman, senior consultant at Global Asia Consulting, said extending the testing period is a principled decision, not an unnecessary delay.
“It prioritises system reliability and passenger safety. Rushing the launch could lead to trains stopping mid-track, brake failures, repeated delays, and a damaged public image

"Addressing all issues before operations start prevents costly repairs and long-term negative perception," he noted in the same report.
Source: The star.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRA2444
SELANGOR
BSQ3640
JOHOR
JYX3040
PULAU PINANG
PSC5019
PERAK
APH6757
PAHANG
CFG6020
KEDAH
KGG2171
NEGERI SEMBILAN
NEK4872
KOTA KINABALU
SJR9999*
KUCHING
QAB8428N
Last updated 27 May, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
LRT3 Shah Alam Line Expected To Open In June
After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.
05-02-2026
Prasarana Ridership Jumps 11% in 2025
Prasarana ridership jumps 11% in 2025 hitting 1.31 million users.
07-01-2026
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete
The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.
29-07-2024
Latest News
3,500+ Proton Drivers Choose ChargeSini for Home Installation, Here’s Why
Buying a Proton e.MAS? Discover why 3,500+ drivers choose ChargeSini for home EV charger installation. Get a 10% public promo!
26-05-2026
Genting "Toll" Starts May 28, But Here Is Why Malaysian Bikers Are Celebrating The New Rules
Lingkaran Cekap Sdn Bhd introduces a new RM5 road charge for cars entering Jalan Genting Highlands starting May 28, 2026, while motorcycles receive full exemption.
26-05-2026
JPJ Terengganu Calls Out Young Riders Over Alarming Rise In Riding Unlicensed & Helmetless
Terengganu JPJ Director Mohd Zamri Samion calls out the casual attitude (sikap sambil lewa) of young motorcyclists riding unlicensed and helmetless.
26-05-2026
Anthony Loke Forces Vulnerable JPJ Systems Back Online Despite Active Fraud Exposure
Transport Minister Anthony Loke instructs JPJ to postpone its online vehicle transfer system upgrade to the long weekend, keeping the system active despite major fraud warnings.
25-05-2026
The End of Crazy Price Drops: A Market Analyst Says EV Pricing Is Finally Becoming "Rational" In Malaysia
A CIMB Securities automotive analyst reveals why MITI’s new July 1 CBU EV policy will end aggressive price wars and push imported EV showroom prices past RM300k.
25-05-2026
10 BIG Reasons To Visit KLIMS 2026 Even If You’re Not A Car Enthusiast
Discover 10 massive reasons to visit KLIMS 2026 at MITEC from June 12–21, featuring free weekday entry, live RIUH concerts, a Pokémon truck, simulators, and smart transit options.
21-05-2026
Game Over, Tonto! JPJ Teams Up With MACC To Hunt Down Secret Lorry Informant Syndicates
JPJ partners with the MACC to dismantle a secret "tonto" sticker syndicate helping heavy commercial lorries evade law enforcement checkpoints.
21-05-2026
254,000 Cars Sold So Far In 2026! A Look At Which Malaysian States Are Freezing In Traffic
Over 254,000 new cars have hit Malaysian roads in the first 4 months of 2026. Discover how MAA’s April sales surged 17% as vehicle production ramped up post-Raya.
20-05-2026
Show More
trending_flat