Bukit Chagar RTS Link Station Roof Completed, Final Facade Works Underway
The Johor Bahru–Singapore RTS Link has taken another big step forward, with MRT Corp confirming that the main roof structure at Bukit Chagar station is now complete, marking a key transition into the project’s final construction phase.
The roof, made up of large steel facade bands, now provides permanent protection over the station platforms.
With this in place, contractors have been able to remove temporary shelters above the tracks, opening up the site and allowing work on platforms, architectural elements and system installations to move ahead more smoothly.
This development also signals the start of the last phase of facade works, with external cladding and glass installation already under way. Once finished, the station is expected to become a standout landmark for Johor Bahru, both visually and functionally.
“This milestone goes beyond completing a physical structure. It reflects how national infrastructure can promote Malaysian capability, collaboration and excellence,” said MRT Corp chief executive Datuk Mohd Zarif Hashim.
He noted that the station’s facade carries special meaning, as its final design, fabrication and installation were entirely handled by Malaysian contractors.
The facade itself was conceived as a gateway into Johor Bahru and a symbol of the close ties between Malaysia and Singapore. Its design was selected through a national architectural competition in 2020, with MRT Corp and an international consultant later confirming its feasibility.
In terms of scale, the structure is substantial. The roof stands about 50 metres high, stretches 200 metres long and spans 50 metres wide, featuring 16 steel bands, along with a rainscreen system, skylights and a spire.
"Fabrication works were carried out across facilities in Bentong, Seremban and Tapah, covering more than 40,000 square metres to meet engineering and quality requirements," he added.

With major structural works now in place, MRT Corp said the focus is firmly on operational readiness, ensuring the RTS Link is completed safely and on schedule.
Once operational, the 4km RTS Link shuttle will connect Bukit Chagar station in Johor Bahru to Woodlands North station in Singapore, and is expected to handle up to 10,000 passengers per hour in each direction during peak periods, easing cross-border travel significantly.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VSA8652
SELANGOR
BSV3534
JOHOR
JH9503J
PULAU PINANG
PSH6158
PERAK
APN2791
PAHANG
CFJ4872
KEDAH
KGJ9561
NEGERI SEMBILAN
NEM6948
KOTA KINABALU
SJV3290
KUCHING
QAB1027Q
Last updated 25 Nov, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
RTS Link On Track As Bukit Chagar Hub Completed
The Johor Bahru-Singapore RTS Link has completed its Bukit Chagar terminal and remains on track for launch by end-2026.
30-07-2025
Penang LRT Stays Within RM16 Billion Budget - MRT Corp
Penang LRT project capped at RM16 billion, with MRT Corp aiming to deliver a cost-efficient system despite rising expenses.
30-07-2025
LOKE: MRT Ridership Increasing Despite Losses Due To Upkeep
MRT ridership has significantly increased despite MRT Corp is still in the red due to high capital expenditures.
11-07-2024
Penang’s LRT Will Extend To Butterworth Via Rail Bridge
Penang's first LRT line will feature a cross-channel link in the form of a rail bridge that will connect the island directly to Butterworth.
14-02-2024
Parking Spots Reserved For Staff, Disabled - MRT Corp
Parking spaces at Jalan Rimbunan Raya 1 near the Kepong Baru MRT station for staff and disabled says MRT corp.
08-06-2023
"Too early to assess Putrajaya MRT route on peak-hour congestion" - Loke
It is still too early to assess the effectiveness of Putrajaya's MRT service in reducing traffic congestion, says Loke.
07-04-2023
PM Announces Free MRT Putrajaya Line Fares Until End Of March
PM inaugurated the full launch of MRT Putrajaya Line plus announced free fares starting March 16 to 31, 2023.
16-03-2023
MRT Putrajaya Line Phase Two Expected To Lessen Traffic Congestion Heading To KL
MRT Putrajaya Line Phase Two is expected to reduce traffic congestion to the city centre.
13-03-2023
Latest News
JPJ Requires Updated Address, Email And Phone Number Details
JPJ requires updated address, email and phone details. Here's what Malaysians need to check, how to update their information and what JPJ says about deadlines.
24-11-2026
Penang ANPR: 27,734 Parking Fines Cancelled, Future Plans Explained
Penang has no plans to resume ANPR parking enforcement after cancelling 27,734 fines and refunding RM203,170. Here's what drivers should know.
23-11-2026
Yangwang U9 And U8 To Be Displayed In Malaysia At MATRADE, Nov 27–29
The Yangwang U9 and U8 are coming to Malaysia for a special showcase at MATRADE from Nov 27–29. Here's where to see them and what makes them special.
23-11-2026
Police Roadblock Malaysia: What To Do If An Officer Asks For Money
Asked for money at a police roadblock in Malaysia? Learn how to identify unofficial payments, stay safe and report suspected police bribery.
23-11-2026
Kelantan Flood Forecast Nov 24–27: Jeli, Pasir Mas, Tanah Merah And Tumpat At Risk
Kelantan flood forecast Nov 24–27: Jeli, Pasir Mas, Tanah Merah and Tumpat at risk. Here's what drivers should check before travelling.
23-11-2026
Women Want Female E-Hailing Drivers. But Are There Enough Options In Malaysia?
Looking for female e-hailing drivers in Malaysia? Explore women-only rides, service availability, passenger safety and legal transport requirements.
18-11-2026
Malaysia Toll Abolition Explained: RM400 Billion And Highway Concessions
Why could abolishing Malaysia's highway tolls cost RM400 billion? Explore highway concessions, toll payments and alternatives to nationwide toll abolition.
17-11-2026
GWM Malaysia 2026 Year-End Deals: Prices, Warranties And Financing Offers
GWM Malaysia's 2026 year-end deals include the ORA Good Cat from RM94,000, Haval H6 HEV privileges, WEY G9 financing and Tank SUV warranties.
16-11-2026
Show More
trending_flat
Malaysia First Used Car and EV Consignment Platform
This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

Understanding CariCarzAutomall Consignment Plan


Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge