ECRL Project, Aims to Operate by 2027

Jesica Sendai

Share via

Recently, Prime Minister Datuk Seri Ismail Sabri Yaakob has officiated a ceremony to mark the start of Genting Tunnel excavation under the East Coast Rail Link (ECRL) first tunnel boring machine (TBM1) project.

The project costs more than 50 million and could enhance connectivity between Selangor and the east coast states including transport cargo from Port Klang to Port Kuantan. 

Apart from that, it benefitted young people especially 5,000 youths from east coast as it has the potential to produce more highly skilled locals through ECRL Industrial Skills Training Programme (PLKI-ECRL).


Tunnel Boring Machine (TBM1) is predicted to complete approximately 2 and a half years to three years to break through 16.39km Genting Tunnel which costs an average excavation amount of between 400m and 600m per month. 

Once the tunnel project is accomplished, it will become the longest rail tunnel in the South-east Asia region which expected to operate in January 2027 having 665 kilometres distance across Kelantan, Terengganu, Pahang, and Selangor.

More uniquely, this tunnel excavation is the only among 59 tunnels drilling to use the TBM method, compared to the drilling and blasting methods for previous tunnels.


With a speed of 160kph, the journey is more convenient and safer for passengers to travel to the east coast. 

Total of 20 stations, consisting of 10 passenger stations and a mix of passenger and cargo stations, the ECRL is also connected to the LRT Kelana Jaya Line at ITT Gombak, thus reducing travel time to Kelantan to 4 hours compared to 7 to 12 hours of journey during festive season. 

TBM1 is a state-of-the-art machine built made for this project and is the largest rail construction machine in South-east Asia to convey through Titiwangsa Range along the Bukit Tinggi area which link Bentong with Gombak, Selangor.

THE East Coast Rail Link (ECRL) is under the partnership project between Malaysia Rail Link Sdn Bhd (MRL) and China Communications Construction Co Ltd (CCCC). 


Tagged:

ECRL
Share This Article

Written By

Jesica Sendai

from 9 to 5 grinder to 'racing' her way in the automotive industry through editorial work.

Share via

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023

Latest News

Auto News
No Extra Cost, But Check Your Filter? 4 Essential Things Every Diesel Driver Needs To Know About The B15 Rollout

No Extra Cost, But Check Your Filter? 4 Essential Things Every Diesel Driver Needs To Know About The B15 Rollout

Malaysia officially rolled out the B15 biodiesel blend on June 1. Find out if your Hilux, Ranger, Triton, or Mazda diesel engine is compatible based on latest manufacturer statements.

03-06-2026
Auto News
APAD Demands Answers: Prasarana Ordered To Submit Urgent Report Following Scary LRT Derailment In KL

APAD Demands Answers: Prasarana Ordered To Submit Urgent Report Following Scary LRT Derailment In KL

APAD launches an immediate independent investigation into Prasarana following the Ampang Line LRT train derailment near Chan Sow Lin station due to a faulty track switch.

29-05-2026
Auto News
Up to RM200,000 Off?! Sime Motors MotorExpo 2026 Is Bringing the Biggest Car Rebates of the Year to KL

Up to RM200,000 Off?! Sime Motors MotorExpo 2026 Is Bringing the Biggest Car Rebates of the Year to KL

Secure the biggest car discounts of the year at Sime Motors MotorExpo 2026 from June 5-7 at XOX Arena KL, featuring rebates up to RM200,000 across 10 elite brands.

29-05-2026
Auto News
Proton Delivered Real Engines To These 6 Malaysian TVET Hubs And Universities

Proton Delivered Real Engines To These 6 Malaysian TVET Hubs And Universities

Proton delivers advanced factory production engine units to 6 Malaysian TVET hubs and universities, including UTHM, UMPSA, and ILP Marang, with plans for future EV parts.

28-05-2026
Auto News
Infographic Reveals Which ASEAN Country Has The Cheapest Fuel (Spoiler: Malaysia Is In The Top 2!)

Infographic Reveals Which ASEAN Country Has The Cheapest Fuel (Spoiler: Malaysia Is In The Top 2!)

An official Information Department infographic reveals Malaysia has the second cheapest RON 95 petrol in ASEAN at RM1.99/L via Budi Madani, trailing only Brunei.

28-05-2026
Auto News
"If You Build A Service Center, We Pay For It" — Volt Auto’s Massive Cash Injection To Upgrade Dongfeng Malaysia

"If You Build A Service Center, We Pay For It" — Volt Auto’s Massive Cash Injection To Upgrade Dongfeng Malaysia

Volt Auto CEO Soh Ming announces 100% funding for local Dongfeng service centers in Malaysia, enforcing strict 70% after-sales showroom requirements alongside 2026 CKD assembly plans.

28-05-2026
Auto News
3,500+ Proton Drivers Choose ChargeSini for Home Installation, Here’s Why

3,500+ Proton Drivers Choose ChargeSini for Home Installation, Here’s Why

Buying a Proton e.MAS? Discover why 3,500+ drivers choose ChargeSini for home EV charger installation. Get a 10% public promo!

26-05-2026
Auto News
Genting "Toll" Starts May 28, But Here Is Why Malaysian Bikers Are Celebrating The New Rules

Genting "Toll" Starts May 28, But Here Is Why Malaysian Bikers Are Celebrating The New Rules

Lingkaran Cekap Sdn Bhd introduces a new RM5 road charge for cars entering Jalan Genting Highlands starting May 28, 2026, while motorcycles receive full exemption.

26-05-2026