Once the East Coast Rail Link (ECRL) is finished, it will only take four hours to travel from Kelantan to Kuala Lumpur, according to Datuk Seri Dr Wee Ka Siong.

The trip presently takes seven to eight hours and, as of June, the ECRL stands 31.48% finished.

The initial proposal for the High Speed Rail (HSR) connection between Kuala Lumpur and Singapore was abandoned in January 2021, according to the Transport Minister.

"After a meeting between the Prime Minister and the Prime Minister of Thailand, there was a proposal to link the HSR from Kuala Lumpur to Bangkok," said Dr Wee on his Facebook page.

On Tuesday, July 19, Pontian MP Datuk Seri Ahmad Maslan questioned the condition of the ECRL, HSR, Pan Borneo, MRT, and new highways to ease traffic congestion in Parliament.

According to Dr. Wee, it was decided in May to form a special committee between the transport ministries of Malaysia and Thailand, which would be presided over by both secretaries general, to talk about the project's planning, alignment, and technical issues.

"As a mega project, the Transport Ministry has to look at the development of the project on a bigger scale, which is a link to the mainland of Asean," he said.

Dr. Wee stated that the project on MRT2, which started in October 2015, will be finished in January. According to him, the MRT2 project was 98.4 percent finished as of June.

He also added that on June 16, operations on the 17.5 kilometre Phase 1 Putrajaya link between Kampung Batu and Damansara Power Station got underway.

"This phase, which has 12 stations, is providing service to high-density areas such as Sungai Buloh, Damansara Damai and Sri Damansara in Petaling Jaya, Kepong, Jinjang and Kampung Batu in Kuala Lumpur," he said.

On the Pan Borneo Highway, Dr Wee said the toll reduction was under the jurisdiction of the Works Ministry.

"The project will not only improve the road connectivity of Sabah and Sarawak, but also to Brunei.

"The Works Ministry is presently carrying out discussions on restructuring with the concessionaires to find a solution on the toll rates," added Dr Wee.


Gallery

Tagged:

ECRL
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023

Latest News

Auto News

Buying A Car Soon? 5 Big Changes That Took Effect On 1 June That You Need To Know

Buying a car in Malaysia? The Hire-Purchase Amendment Act 2026 took effect on 1 June. Here are 5 new rules on EIR and car loan interest you must know.

03-06-2026
Auto News

No Extra Cost, But Check Your Filter? 4 Essential Things Every Diesel Driver Needs To Know About The B15 Rollout

Malaysia officially rolled out the B15 biodiesel blend on June 1. Find out if your Hilux, Ranger, Triton, or Mazda diesel engine is compatible based on latest manufacturer statements.

03-06-2026
Auto News

APAD Demands Answers: Prasarana Ordered To Submit Urgent Report Following Scary LRT Derailment In KL

APAD launches an immediate independent investigation into Prasarana following the Ampang Line LRT train derailment near Chan Sow Lin station due to a faulty track switch.

29-05-2026
Auto News

Up to RM200,000 Off?! Sime Motors MotorExpo 2026 Is Bringing the Biggest Car Rebates of the Year to KL

Secure the biggest car discounts of the year at Sime Motors MotorExpo 2026 from June 5-7 at XOX Arena KL, featuring rebates up to RM200,000 across 10 elite brands.

29-05-2026
Auto News

Proton Delivered Real Engines To These 6 Malaysian TVET Hubs And Universities

Proton delivers advanced factory production engine units to 6 Malaysian TVET hubs and universities, including UTHM, UMPSA, and ILP Marang, with plans for future EV parts.

28-05-2026
Auto News

Infographic Reveals Which ASEAN Country Has The Cheapest Fuel (Spoiler: Malaysia Is In The Top 2!)

An official Information Department infographic reveals Malaysia has the second cheapest RON 95 petrol in ASEAN at RM1.99/L via Budi Madani, trailing only Brunei.

28-05-2026
Auto News

"If You Build A Service Center, We Pay For It" — Volt Auto’s Massive Cash Injection To Upgrade Dongfeng Malaysia

Volt Auto CEO Soh Ming announces 100% funding for local Dongfeng service centers in Malaysia, enforcing strict 70% after-sales showroom requirements alongside 2026 CKD assembly plans.

28-05-2026
Auto News

3,500+ Proton Drivers Choose ChargeSini for Home Installation, Here’s Why

Buying a Proton e.MAS? Discover why 3,500+ drivers choose ChargeSini for home EV charger installation. Get a 10% public promo!

26-05-2026