LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing

Kumeran Sagathevan

Share via

LRT3-ShahAlam-Line-(1)-full_normal.jpg


Although solutions have been developed for all 33 technical issues flagged on the LRT3 Shah Alam Line, the systems have yet to complete full testing to confirm they perform reliably under operating conditions.

According to Sinar Harian, Shah Alam Line COO Mohd Ariffin Idris said the project team is now focused on extended and continuous testing, aimed at validating whether the fixes introduced truly resolve the problems encountered earlier.


482007087_633007019374783_2319286765909882135_n.jpg

He explained that while corrective measures are already in place, they must be proven through rigorous trials before the line can be considered operationally ready. Testing, he said, is still ongoing and remains a critical phase of the project.

A major area of attention is the system software, which is being upgraded to the latest baseline to ensure it can cope with both existing faults and any new issues that may emerge during testing.

Mohd Ariffin added that failure-free run (FFR) testing is currently being carried out on all trains assigned to the Shah Alam Line. A total of 22 trains must undergo the process, with each test monitored by the Land Public Transport Agency (APAD) as part of standard regulatory requirements.


481670118_633007029374782_6626559310987309250_n.jpg


Even trains that have already clocked the required mileage are not exempt, as they still need to be reassessed to ensure every technical and safety criterion is fully satisfied.

According to him, the line cannot open to passengers until all trains pass FFR testing and the entire system, including infrastructure and signalling, is confirmed to be fully complete and stable.

Testing is conducted around the clock, including overnight sessions, with specialists from original equipment manufacturers involved to address specific technical challenges. These include signalling systems supplied from Germany and rolling stock sourced from China.

He noted that uncovering new issues during dry runs is not unusual, and any problems identified will be rectified before further testing continues to ensure long-term stability.


PANEL-A-Quick-Facts-2.png


As for the start of public operations, Mohd Ariffin said an official projection is expected to be announced by senior management around January next year, once testing reaches a more conclusive stage.

Earlier reports by Prasarana Malaysia Bhd revealed that the 33 technical issues, largely linked to software errors and system disruptions, were identified during two and a half months of testing and were a key reason behind delays to the line’s launch.

Among the problems detected were trains failing to stop precisely at platforms, issues with door operations, incorrect speed settings, failures in automatic train movement, and unintended train movement when the system should have remained static.


Tagged:

LRT3 Shah Alam Line
Light Rapid Transit 3 (LRT3)
Shah Alam Line (LRT3)
Share This Article

Written By

Kumeran Sagathevan

More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!

Share via

Related News

Auto News

Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far

The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.

05-03-2026
Auto News

LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays

The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.

24-02-2026
Auto News

LRT3 Shah Alam Line Expected To Open In June

After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.

05-02-2026
Auto News

Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash

Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.

15-12-2025
Auto News

LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set

The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.

12-12-2025
Auto News

LRT3 Enters Final Testing Phase, Govt Targets Dec 31 Opening

LRT3 line is now in its final round of safety and reliability tests, with its launch date hinging on Dec results.

18-11-2025
Auto News

Shah Alam LRT Delayed Again, December Now In Sight

The Shah Alam LRT may miss its September deadline, with Prasarana now aiming for a December launch pending crucial safety tests.

26-08-2025
Auto News

LRT3 Shah Alam Line Opening Could Be Delayed to Oct 31 – Report

The LRT3 Shah Alam line opening could be delayed until Oct 31 instead of the planned launch date of Sept 30.

04-08-2025

Latest News

Auto News

Buying A Car Soon? 5 Big Changes That Took Effect On 1 June That You Need To Know

Buying a car in Malaysia? The Hire-Purchase Amendment Act 2026 took effect on 1 June. Here are 5 new rules on EIR and car loan interest you must know.

03-06-2026
Auto News

No Extra Cost, But Check Your Filter? 4 Essential Things Every Diesel Driver Needs To Know About The B15 Rollout

Malaysia officially rolled out the B15 biodiesel blend on June 1. Find out if your Hilux, Ranger, Triton, or Mazda diesel engine is compatible based on latest manufacturer statements.

03-06-2026
Auto News

APAD Demands Answers: Prasarana Ordered To Submit Urgent Report Following Scary LRT Derailment In KL

APAD launches an immediate independent investigation into Prasarana following the Ampang Line LRT train derailment near Chan Sow Lin station due to a faulty track switch.

29-05-2026
Auto News

Up to RM200,000 Off?! Sime Motors MotorExpo 2026 Is Bringing the Biggest Car Rebates of the Year to KL

Secure the biggest car discounts of the year at Sime Motors MotorExpo 2026 from June 5-7 at XOX Arena KL, featuring rebates up to RM200,000 across 10 elite brands.

29-05-2026
Auto News

Proton Delivered Real Engines To These 6 Malaysian TVET Hubs And Universities

Proton delivers advanced factory production engine units to 6 Malaysian TVET hubs and universities, including UTHM, UMPSA, and ILP Marang, with plans for future EV parts.

28-05-2026
Auto News

Infographic Reveals Which ASEAN Country Has The Cheapest Fuel (Spoiler: Malaysia Is In The Top 2!)

An official Information Department infographic reveals Malaysia has the second cheapest RON 95 petrol in ASEAN at RM1.99/L via Budi Madani, trailing only Brunei.

28-05-2026
Auto News

"If You Build A Service Center, We Pay For It" — Volt Auto’s Massive Cash Injection To Upgrade Dongfeng Malaysia

Volt Auto CEO Soh Ming announces 100% funding for local Dongfeng service centers in Malaysia, enforcing strict 70% after-sales showroom requirements alongside 2026 CKD assembly plans.

28-05-2026
Auto News

3,500+ Proton Drivers Choose ChargeSini for Home Installation, Here’s Why

Buying a Proton e.MAS? Discover why 3,500+ drivers choose ChargeSini for home EV charger installation. Get a 10% public promo!

26-05-2026