ECRL Is Underway; More Than 30% Completed – Dr Wee Ka Siong
Once the East Coast Rail Link (ECRL) is finished, it will only take four hours to travel from Kelantan to Kuala Lumpur, according to Datuk Seri Dr Wee Ka Siong.
The trip presently takes seven to eight hours and, as of June, the ECRL stands 31.48% finished.
The initial proposal for the High Speed Rail (HSR) connection between Kuala Lumpur and Singapore was abandoned in January 2021, according to the Transport Minister.
"After a meeting between the Prime Minister and the Prime Minister of Thailand, there was a proposal to link the HSR from Kuala Lumpur to Bangkok," said Dr Wee on his Facebook page.
On Tuesday, July 19, Pontian MP Datuk Seri Ahmad Maslan questioned the condition of the ECRL, HSR, Pan Borneo, MRT, and new highways to ease traffic congestion in Parliament.
According to Dr. Wee, it was decided in May to form a special committee between the transport ministries of Malaysia and Thailand, which would be presided over by both secretaries general, to talk about the project's planning, alignment, and technical issues.
"As a mega project, the Transport Ministry has to look at the development of the project on a bigger scale, which is a link to the mainland of Asean," he said.
Dr. Wee stated that the project on MRT2, which started in October 2015, will be finished in January. According to him, the MRT2 project was 98.4 percent finished as of June.
He also added that on June 16, operations on the 17.5 kilometre Phase 1 Putrajaya link between Kampung Batu and Damansara Power Station got underway.
"This phase, which has 12 stations, is providing service to high-density areas such as Sungai Buloh, Damansara Damai and Sri Damansara in Petaling Jaya, Kepong, Jinjang and Kampung Batu in Kuala Lumpur," he said.
On the Pan Borneo Highway, Dr Wee said the toll reduction was under the jurisdiction of the Works Ministry.
"The project will not only improve the road connectivity of Sabah and Sarawak, but also to Brunei.
"The Works Ministry is presently carrying out discussions on restructuring with the concessionaires to find a solution on the toll rates," added Dr Wee.
Gallery
Tagged:
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQT2420
SELANGOR
BSP108
JOHOR
JYU4311
PULAU PINANG
PSB2687
PERAK
APG4941
PAHANG
CFG1524
KEDAH
KGF1925
NEGERI SEMBILAN
NEJ9813
KOTA KINABALU
SJR2795
KUCHING
QAB5250N
Last updated 11 Apr, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
Latest News
A Sense of Crisis: What Toyota, Ford, and Honda’s Leadership are Saying About the Future
Legacy automakers are facing a 'Change or Die' moment. From Honda's $15.8 billion loss to Toyota's survival warning, see why 'China Speed' is winning.
11-04-2026
Why Is Global Oil Falling But Our Petrol Price Is Still High? — MOF Explains The 'Lag'
Why is global oil falling but Malaysia’s petrol price is still high? MOF explains the APM "lag effect" and why unsubsidized RON95 hit RM4.27 this week.
10-04-2026
Proton X50 ‘Black Edition' Look Goes Permanent: Quartz Black Now Available for All Variants
Proton X50 Quartz Black is now permanent for all variants!
09-04-2026
SUPER GT 2026 Malaysia Might Not Happen At All? Here’s What We Know So Far
Is SUPER GT 2026 Malaysia cancelled? Reports suggest the Malaysian round may be called off due to fuel concerns and high costs. Get the latest updates here.
07-04-2026
Is It Illegal To Borrow Your Parents' MyKad For Subsidised Petrol? Here’s What The Law Says
Can you use a family member's MyKad for Budi95 petrol? JPN warns that sharing IDs at the pump is prohibited and under investigation. Get the official rules here.
06-04-2026
Tough Times, But Everyone Still Wants a Saga: Sales Jump 38% Despite a Slow Market
Proton Saga defies the 2026 market slump with a 38% sales surge! Discover the new 1.5L engine, Level 1 ADAS, and tech upgrades making it Malaysia’s top choice.
03-04-2026
Malaysia Is Angry… But The World Is Already in Energy Crisis
Malaysia is cutting the BUDI95 quota to 200L. While we argue over liters, the world is in "Energy Survival Mode." Is an EV your secret to beating the 2026 crisis?
03-04-2026
GWM Malaysia Eyes Top 10 Spot by 2028: 6 New Models to Launch, Led by Tank 300 HEV
GWM Malaysia targets Top 10 status by 2028, launching 6 new SUVs starting with the Tank 300 HEV.
02-04-2026
Show More
trending_flat