Ampang/Sri Petaling LRT Line Repair Works To Take Up To 7 Months

Minister of Transport, YB Anthony Loke earlier today announced that the investigation on the structural damage of the viaduct and the cracked pier near the Bandaraya LRT station is complete. This service interruption between the Masjid Jamek LRT station and the Bandaraya LRT station happened on 27 Jan 27 2023.
The investigation shows that damages to the three viaduct structures and the pier was caused by "ground movement" believed to be from works at the adjacent construction site. According to the Land Public Transport Agency (APAD), the construction works were performed without any consultation with APAD under the Railway (Railway Protection Zone) Regulations 1998 [P.U. (A) 367].
-full_normal.jpg)
Prasarana, the concession holder for Rapid KL is now in the process of appointing a contractor to carry out the repair work which is expected to start in early March and would take up to seven months to complete.
These seven months would include two months for strengthening of the structure and five months for comprehensive repair works. Prasarana would be looking into legal action against the developer for the damages incurred.
-full_normal.jpg)
Once the Putrajaya Line MRT service is operational this coming March, users of the Ampang/Sri Petaling Line will have an alternative route to the city centre via interchange stations such as Chan Sow Lin, Titiwangsa and Sg Besi.
While the repair works are being carried out, Rapid KL would continue the feeder bus service which has been ongoing since 27 Jan.
Gallery
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRN8297
SELANGOR
BST4507
JOHOR
JD6041J
PULAU PINANG
PSF3293
PERAK
APL2531
PAHANG
CFH6254
KEDAH
KGH8707
NEGERI SEMBILAN
NEL6915
KOTA KINABALU
SJT9017
KUCHING
QAB5172P
Last updated 04 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Sri Petaling LRT Line Will Resume Operations On 29 February
Repairs to specific stations along the Sri Petaling LRT line will be completed by the end of February 2024, says Rapid KL.
07-01-2024
Ampang/Sri Petaling LRT Line Repair Completion Delayed Till February 2024
Ampang/Sri Petaling LRT Line, reopening delayed till February 29, 2024
29-09-2023
Govt Won’t Suspend KLIA Aerotrain, MAHB Facing Action - Loke
Loke says the government won’t halt the KLIA Aerotrain, but MAHB is facing action.
30-10-2025
Youths Encroach “Women Only Coach”; KTMB & APAD discuss legislation
A recent incident of harassment in “Women Only Coach”, brings up the call for legislation.
03-09-2024
APAD To Regulate P-Hailing Riders’ Income, Says MOT
The Ministry Of Transport has agreed to allow the Land Public Transport Agency (APAD) in regulating p-hailing service providers.
12-04-2023
APAD Extends Taxi & e-Hailing Vehicles Age Limit to 15 Years
The Malaysian Land Public Transport Agency has increased the age limit for taxi & e-hailing vehicles to 15 years.
03-04-2023
Gerik - Jeli Incident, Transportation Company's License Revoked - APAD
Hence the APAD’s Cancellation and Revocation department concluded to revoke the operator, Mun Fei Enterprise (IM0103026-M) operation license with immediate effect.
28-12-2022
Maxim Cleared To Resume E-Hailing Operations Nationwide
Maxim Malaysia has officially received approval from APAD to continue its e-hailing services.
05-12-2025
Latest News
Kids Spotted Sitting on Moving Alphard Roof in Ipoh: Police Launch Investigation Under Child Act
Ipoh police are tracking a Toyota Alphard driver after a viral video showed two kids sitting on the roof via the sunroof.
03-09-2026
"Traffic Was Slow Before The Tanker Struck": Horrific 11-Vehicle LPT1 Crash Claims 4 Lives Near Temerloh
Four people, including Kuantan’s Secangkir Cafe founders and their 4-year-old son, were killed after an out-of-control cement tanker triggered an 11-vehicle crash on LPT1 near Temerloh. Read the latest police updates.
01-09-2026
Perodua's Supplier Just Dropped A Huge RM54Mil Clue About A Secret New Model Launching In 2027
Perodua supplier MCE Holdings drops an RM54M clue about a secret 2027 model. Read about the upcoming next-gen Myvi, Bezza facelift, and local ADAS tech.
27-08-2026
Proton Almost Built A RM150,000 Mid-Engined Sports Car Using Lotus Tech & Wira Parts
Did you know Proton almost built a RM150k mid-engined sports car? Discover how 'Project Sepang' combined Lotus engineering, Wira parts, and Petronas tech.
26-08-2026
RM1,000 Trade-In Subsidy For Old Motorcycles: Transport Ministry Considers New Scheme
Got an old motor? MOT is considering a RM1,000 trade-in subsidy to help Malaysian riders upgrade to new CKD bikes. Here is how the proposed scheme works.
26-08-2026
Do You REALLY Have To Give Way To Every Siren? What Experts Say About VIP Convoys vs. Emergencies
Do you legally have to give way to VIP convoys in Malaysia? Here is what traffic laws and safety experts say about sirens, outriders, and RM10k fines.
26-08-2026
"Can I Pass My Diesel Quota To My Family?" — 3 Big Changes Coming To Malaysia’s Diesel Subsidy System
KPDN & MOF to launch 3 diesel subsidy updates in less than a month, covering family quota transfers, sambung bayar eligibility, and easier applications.
24-08-2026
Hannah Yeoh & Amirudin Shari Unveil 5 Emergency Steps To Fix Klang Valley Floods Before Budget 2027
Hannah Yeoh & Amirudin Shari unveil a 5-step Klang Valley flood mitigation plan covering dam reviews, retention ponds, and river desilting before Budget 2027.
24-08-2026
Show More
trending_flat