WCE To Serve 300,000 Vehicles When Opened & Is A Safer Highway!

According to Utusan Malaysia, the West Coast Expressway (WCE) and Federal Route 5 (FR5), which span a total length of 275.8 kilometres (km), would accommodate at least 300,000 vehicles per day when completed by the end of next year or early 2025.
The WCE, Malaysia's second longest highway, has the ability to divert up to 20% of traffic from the North-South Motorway (PLUS), which serves 1.8 million users, reducing congestion, particularly in the northern region during holiday seasons.
Moreover, the opening of sections in Bandar Bukit Raja, Hutan Melintang, Lekir, and Changkat Chermin in Perak, specifically Sections 5, 8, 9, and 10 since May 2019, has resulted in a traffic increase of up to 60 percent this year. Since the initial opening of Hutan Melintang, Perak 73.4 km stretch there has been a flow of 35,000 vehicles, which has now risen to an average of 50,000 to 60,000 vehicles per day.

Lyndon Alfred Felix, CEO of WCE Berhad, disclosed that this year will see the opening of four sections: Sections 1, 2, 6, and 11, encompassing areas such as Banting, the South Klang Valley Expressway (SKVE), Assam Jawa, and South Taiping.
Meanwhile Section 4, which serves as the connection to the Federal Highway and is currently 99 percent complete and will be opened once land acquisition matters are resolved around Jalan Kebun for Section 3, linking to Shah Alam Expressway (Kesas).

Lyndon also added that for this coming Hari Raya Haji celebrations, WCE is prepared to accommodate over 100,000 vehicles, surpassing last year's figure of 60,000. WCE would also prove to be a convenient route for residents residing in Shah Alam, Klang, and Kuala Langat, who wish to travel north without encountering traffic from Kuala Lumpur, Hulu Selangor, Gombak, and Hulu Langat.
From a safety perspective, according to him, the WCE offers a safer option with its flat and less winding route, unlike other highways which are built on hilly and hazardous routes making WCE particularly suitable for heavy vehicles.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VQT2420
SELANGOR
BSP108
JOHOR
JYU4311
PULAU PINANG
PSB2687
PERAK
APG4941
PAHANG
CFG1524
KEDAH
KGF1925
NEGERI SEMBILAN
NEJ9813
KOTA KINABALU
SJR2795
KUCHING
QAB5250N
Last updated 11 Apr, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
WCE: Six New Toll Plazas Planned Along Melaka’s 69 KM Stretch
WCE set to add six new tolls along Melaka’s 69 KM stretch to ease congestion and spread out traffic flow.
10-12-2025
WCE Reports 48% Jump In Toll Revenue, Eyes Full Completion By 2027
Toll collections on the WCE surged 48% in Q2 to RM44.1 million, with the firm aiming for full completion by March 2027.
27-11-2025
Court Upholds Land Takeover For WCE Despite Residents’ Complaint
Judge rules the acquisition for WCE valid even without direct notice, as Kampung Jawa landowners gear up for a crucial valuation hearing.
26-11-2025
WCE Road Closure on Nov 9 For Klang Royal City Marathon 2025
Parts of West Coast Expressway (WCE) will temporarily close for Klang Royal City Marathon on Sunday, Nov 9 2025.
06-11-2025
Selangor Govt Will Decide Fate Of 19 WCE-Affected Residents
The Selangor govt is set to decide soon on the fate of 19 Kampung Jawa residents affected by the West Coast Expressway project.
03-11-2025
Hauliers Warn WCE Delays Hurting Logistics and Economy
The Association of Malaysian Hauliers says delays in completing Section 3 of the WCE are disrupting cargo flow and driving up costs.
29-09-2025
West Coast Expressway On Track For 2027 Completion
The West Coast Expressway is on track for full completion by 2027, with eight of its 11 sections already open.
27-08-2025
Hauliers Demand Swift WCE Land Fix
Association of Malaysian Hauliers urges swift resolution of land disputes delaying completion of the WCE Section 3.
11-08-2025
Latest News
A Sense of Crisis: What Toyota, Ford, and Honda’s Leadership are Saying About the Future
Legacy automakers are facing a 'Change or Die' moment. From Honda's $15.8 billion loss to Toyota's survival warning, see why 'China Speed' is winning.
11-04-2026
Why Is Global Oil Falling But Our Petrol Price Is Still High? — MOF Explains The 'Lag'
Why is global oil falling but Malaysia’s petrol price is still high? MOF explains the APM "lag effect" and why unsubsidized RON95 hit RM4.27 this week.
10-04-2026
Proton X50 ‘Black Edition' Look Goes Permanent: Quartz Black Now Available for All Variants
Proton X50 Quartz Black is now permanent for all variants!
09-04-2026
SUPER GT 2026 Malaysia Might Not Happen At All? Here’s What We Know So Far
Is SUPER GT 2026 Malaysia cancelled? Reports suggest the Malaysian round may be called off due to fuel concerns and high costs. Get the latest updates here.
07-04-2026
Is It Illegal To Borrow Your Parents' MyKad For Subsidised Petrol? Here’s What The Law Says
Can you use a family member's MyKad for Budi95 petrol? JPN warns that sharing IDs at the pump is prohibited and under investigation. Get the official rules here.
06-04-2026
Tough Times, But Everyone Still Wants a Saga: Sales Jump 38% Despite a Slow Market
Proton Saga defies the 2026 market slump with a 38% sales surge! Discover the new 1.5L engine, Level 1 ADAS, and tech upgrades making it Malaysia’s top choice.
03-04-2026
Malaysia Is Angry… But The World Is Already in Energy Crisis
Malaysia is cutting the BUDI95 quota to 200L. While we argue over liters, the world is in "Energy Survival Mode." Is an EV your secret to beating the 2026 crisis?
03-04-2026
GWM Malaysia Eyes Top 10 Spot by 2028: 6 New Models to Launch, Led by Tank 300 HEV
GWM Malaysia targets Top 10 status by 2028, launching 6 new SUVs starting with the Tank 300 HEV.
02-04-2026
Show More
trending_flat