ECRL Project Achieved 52.9 Percent Completion
The East Coast Rail Link (ECRL) project has reached 52.9 percent completion and is expected to be completed by 2027, The Star reported.
According to Transport Minister Anthony Loke Siew Fook, major construction works such as beam launching, structural work and track laying are currently underway along the ECRL line.
Loke also stated that the ECRL project from Kota Baru, Kelantan to Gombak is scheduled to be completed on December 31, 2026, with the stretch from Gombak to Port Klang scheduled to be completed on December 31, 2027. -full-full_normal.jpg)
"Following this, the tunnel borring works for the first tunnel in Genting has reached 3.1 kilometres (km), while the second Genting tunnel has reached 4.29 km.
"At the same time, a total of 25 tunnels have been penetrated as of Aug 25, including 21 tunnels in Section A and B of the project, while the remaining four in Section C," he said.
Meanwhile, he stated that the ECRL corridor would have an agglomeration (assemblage) effect, increasing job opportunities and serving as an economic centre to stimulate economic growth.

At the same time, Loke stated that the project site had been finalised and approved by relevant technical agencies, with more than 70% completion.
He stated that ECRL developers discovered the area to be prone to flooding through studies conducted by hydrology and hydraulics consultants on previous flood situations in the area.
"Following this, they proposed an optimal design, by taking into account technical aspects, value engineering and flood risk in the area. "The ministry will also ensure that the project's main developer, Malaysia Rail Link Sdn Bhd (MRL), alongside its main contractor, China Communications Construction Company (CCCC) maintains public safety during project implementation."
MRL and CCCC signed a supplementary agreement in 2019 to restart the ECRL project at a lower cost.
The new ECRL alignment is now 40 kilometres shorter, from 688 kilometres to 648 kilometres, because it no longer tunnels through the Titiwangsa Main Range, which separates Selangor and Pahang. It runs south from Kota Baru to Port Klang, passing through Mentakab, Jelebu, Kuala Kelawang, Bangi/Kajang, and Putrajaya.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQT2541
SELANGOR
BSP261
JOHOR
JYU4385
PULAU PINANG
PSB2760
PERAK
APG4974
PAHANG
CFG1532
KEDAH
KGF2088
NEGERI SEMBILAN
NEJ9821
KOTA KINABALU
SJR2836
KUCHING
QAB5264N
Last updated 13 Apr, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
The End of RM1.99? World Bank Urges RM2.05 Price Tweak
The World Bank urges Malaysia to raise RON95 petrol prices to RM2.05. With a RM4 billion monthly subsidy bill and Brent crude at US$100, find out why the RM1.99 era might be ending.
13-04-2026
From Wok to Work: FELDA’s B100 Biodiesel Can Fix the Diesel Price Crisis?
FELDA Chairman Ahmad Shabery Cheek reveals how B100 Biodiesel (Palm Oil) could fix Malaysia's diesel price crisis. Learn about the RM4.50 price target and the 50,000km engine trials.
13-04-2026
A Sense of Crisis: What Toyota, Ford, and Honda’s Leadership are Saying About the Future
Legacy automakers are facing a 'Change or Die' moment. From Honda's $15.8 billion loss to Toyota's survival warning, see why 'China Speed' is winning.
11-04-2026
Why Is Global Oil Falling But Our Petrol Price Is Still High? — MOF Explains The 'Lag'
Why is global oil falling but Malaysia’s petrol price is still high? MOF explains the APM "lag effect" and why unsubsidized RON95 hit RM4.27 this week.
10-04-2026
Proton X50 ‘Black Edition' Look Goes Permanent: Quartz Black Now Available for All Variants
Proton X50 Quartz Black is now permanent for all variants!
09-04-2026
SUPER GT 2026 Malaysia Might Not Happen At All? Here’s What We Know So Far
Is SUPER GT 2026 Malaysia cancelled? Reports suggest the Malaysian round may be called off due to fuel concerns and high costs. Get the latest updates here.
07-04-2026
Is It Illegal To Borrow Your Parents' MyKad For Subsidised Petrol? Here’s What The Law Says
Can you use a family member's MyKad for Budi95 petrol? JPN warns that sharing IDs at the pump is prohibited and under investigation. Get the official rules here.
06-04-2026
Tough Times, But Everyone Still Wants a Saga: Sales Jump 38% Despite a Slow Market
Proton Saga defies the 2026 market slump with a 38% sales surge! Discover the new 1.5L engine, Level 1 ADAS, and tech upgrades making it Malaysia’s top choice.
03-04-2026
Show More
trending_flat