ECRL Project Progress Surpasses 56% - Loke

Transport Minister Anthony Loke Siew Fook announced that the East Coast Rail Link (ECRL) project has surpassed 56% of its progress as of November, marking a significant milestone.
This development is in line with the project's completion schedule, which calls for the Gombak Integrated Terminal to be completed by December 2026, and the location of Kota Bharu in Kelantan. By January 2027, operational readiness is expected to be achieved.
Minister Loke stressed the project's transition into a new construction phase, involving flyover beam installations, train station, and depot constructions, highlighting this year as the peak construction phase.
According to The Star, the minister also emphasizes that in order to facilitate passenger and cargo train operations, future stages will concentrate on electrification, signaling, and telecommunication system installations. -full.jpg)
When it's completed, residents of Kuantan will only need to travel 1.5 hours to get to Kuala Lumpur instead of the three hours it takes now by road. Minister Loke highlighted that 23,000 laborers were involved in 1,900 construction sites, with drill and blast techniques being used to excavate 26 tunnels.
One of the major turning points will be the 16.39 km Genting twin tunnel, which is currently under construction and should be finished in the second quarter of 2025. More than 60km of flyover beams have been installed over the 145km ECRL flyover. The project's overall goal is to improve transportation infrastructure in Pahang, Terengganu, Kelantan, and Selangor by building 20 stations.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQT2420
SELANGOR
BSP108
JOHOR
JYU4311
PULAU PINANG
PSB2687
PERAK
APG4941
PAHANG
CFG1524
KEDAH
KGF1925
NEGERI SEMBILAN
NEJ9813
KOTA KINABALU
SJR2795
KUCHING
QAB5250N
Last updated 11 Apr, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Latest News
A Sense of Crisis: What Toyota, Ford, and Honda’s Leadership are Saying About the Future
Legacy automakers are facing a 'Change or Die' moment. From Honda's $15.8 billion loss to Toyota's survival warning, see why 'China Speed' is winning.
11-04-2026
Why Is Global Oil Falling But Our Petrol Price Is Still High? — MOF Explains The 'Lag'
Why is global oil falling but Malaysia’s petrol price is still high? MOF explains the APM "lag effect" and why unsubsidized RON95 hit RM4.27 this week.
10-04-2026
Proton X50 ‘Black Edition' Look Goes Permanent: Quartz Black Now Available for All Variants
Proton X50 Quartz Black is now permanent for all variants!
09-04-2026
SUPER GT 2026 Malaysia Might Not Happen At All? Here’s What We Know So Far
Is SUPER GT 2026 Malaysia cancelled? Reports suggest the Malaysian round may be called off due to fuel concerns and high costs. Get the latest updates here.
07-04-2026
Is It Illegal To Borrow Your Parents' MyKad For Subsidised Petrol? Here’s What The Law Says
Can you use a family member's MyKad for Budi95 petrol? JPN warns that sharing IDs at the pump is prohibited and under investigation. Get the official rules here.
06-04-2026
Tough Times, But Everyone Still Wants a Saga: Sales Jump 38% Despite a Slow Market
Proton Saga defies the 2026 market slump with a 38% sales surge! Discover the new 1.5L engine, Level 1 ADAS, and tech upgrades making it Malaysia’s top choice.
03-04-2026
Malaysia Is Angry… But The World Is Already in Energy Crisis
Malaysia is cutting the BUDI95 quota to 200L. While we argue over liters, the world is in "Energy Survival Mode." Is an EV your secret to beating the 2026 crisis?
03-04-2026
GWM Malaysia Eyes Top 10 Spot by 2028: 6 New Models to Launch, Led by Tank 300 HEV
GWM Malaysia targets Top 10 status by 2028, launching 6 new SUVs starting with the Tank 300 HEV.
02-04-2026
Show More
trending_flat