Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

Prime Minister Datuk Seri Anwar Ibrahim calls for the expedited completion of the Pan Borneo Highway project in Sabah, emphasising the importance of avoiding further delays. He has delegated responsibility to the state government to ensure the project, which benefits the people of Sabah, is completed as quickly as possible.
"Pan Borneo Highway in Sarawak is nearly finished, but Sabah's section is still lagging. We've agreed with the Sabah state government to expedite it," Anwar stated.
He also mentioned that the task of overseeing this matter has been entrusted to Works Minister Datuk Seri Alexander Nanta Linggi and Deputy Prime Minister Datuk Seri Fadillah Yusof, stressing his desire for rapid progress so that the people of Sabah can benefit from this multi-billion-ringgit project, the longest highway in Malaysia.
-full_normal.webp)
Unlike toll highways in Peninsular Malaysia, the Pan Borneo Highway in Sabah and Sarawak is toll-free, provided by the government for the public. As of July 29, Nanta reported that Phase 1A of the Pan Borneo Highway in Sabah was 77.41% complete, with full completion expected by 2026. As of now 11 of the 15 work packages have not yet been finished, with four already finished.
Anwar said that, in regards to project delays, he would not take any justifications from any of the parties concerned. He reported on continuing conversations amongst different governmental levels about current problems such as acute poverty, water, flooding, electricity, and infrastructure.
Anwar also added that although problems like potholes that prevent pupils from going to school and improvised suspension bridges made of thin planks were passed down from the previous government, it is the responsibility of the current administration to address them rather than making excuses.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRN8419
SELANGOR
BST4542
JOHOR
JD6102J
PULAU PINANG
PSF3307
PERAK
APL2539
PAHANG
CFH6270
KEDAH
KGH8710
NEGERI SEMBILAN
NEL6926
KOTA KINABALU
SJT9034
KUCHING
QAB5193P
Last updated 04 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway
The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.
07-10-2024
Sabah Pan Borneo Highway Phase 1B Nears Contractor Selection with Q3 Completion Target
Sabah Pan Borneo Highway in final open tender review for 15 of the 19 work packages for Phase 1B of the project.
26-06-2024
Pan Borneo highway status in Sabah and Sarawak
The condition of the Pan Borneo Highway in Sabah and Sarawak
06-12-2022
Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year
Work on the 4.95km Miri Section will move from planning to physical construction in the first quarter of 2026.
04-12-2025
Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year
Work on the 4.95km Miri Section will move from planning to physical construction in the first quarter of 2026.
04-12-2025
Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway
The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.
07-10-2024
Pan Borneo Highway Project Will Be Completed This Year - Nanta
98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed, says the works minister.
13-02-2024
PMX: Perodua EV Launch Confirmed This Month, Set to Be “National Agenda”
PMX confirms Perodua’s first EV will launch by month-end, and will be elevated to a “national agenda”.
11-11-2025
Latest News
Will "Made-in-Malaysia" BYD EVs Become A Reality Soon?
Discover what Sime Motors' Shenzhen trip signals for local assembly (CKD) in Malaysia.
04-09-2026
Kids Spotted Sitting on Moving Alphard Roof in Ipoh: Police Launch Investigation Under Child Act
Ipoh police are tracking a Toyota Alphard driver after a viral video showed two kids sitting on the roof via the sunroof.
03-09-2026
"Traffic Was Slow Before The Tanker Struck": Horrific 11-Vehicle LPT1 Crash Claims 4 Lives Near Temerloh
Four people, including Kuantan’s Secangkir Cafe founders and their 4-year-old son, were killed after an out-of-control cement tanker triggered an 11-vehicle crash on LPT1 near Temerloh. Read the latest police updates.
01-09-2026
Perodua's Supplier Just Dropped A Huge RM54Mil Clue About A Secret New Model Launching In 2027
Perodua supplier MCE Holdings drops an RM54M clue about a secret 2027 model. Read about the upcoming next-gen Myvi, Bezza facelift, and local ADAS tech.
27-08-2026
Proton Almost Built A RM150,000 Mid-Engined Sports Car Using Lotus Tech & Wira Parts
Did you know Proton almost built a RM150k mid-engined sports car? Discover how 'Project Sepang' combined Lotus engineering, Wira parts, and Petronas tech.
26-08-2026
RM1,000 Trade-In Subsidy For Old Motorcycles: Transport Ministry Considers New Scheme
Got an old motor? MOT is considering a RM1,000 trade-in subsidy to help Malaysian riders upgrade to new CKD bikes. Here is how the proposed scheme works.
26-08-2026
Do You REALLY Have To Give Way To Every Siren? What Experts Say About VIP Convoys vs. Emergencies
Do you legally have to give way to VIP convoys in Malaysia? Here is what traffic laws and safety experts say about sirens, outriders, and RM10k fines.
26-08-2026
"Can I Pass My Diesel Quota To My Family?" — 3 Big Changes Coming To Malaysia’s Diesel Subsidy System
KPDN & MOF to launch 3 diesel subsidy updates in less than a month, covering family quota transfers, sambung bayar eligibility, and easier applications.
24-08-2026
Show More
trending_flat