Over 70 Percent Of ECRL Project Completed - Loke
According to Transport Minister Anthony Loke, the East Coast Rail Link (ECRL) project, which spans four states (Pahang, Kelantan, Terengganu, and Selangor), is currently 70.13 percent complete.
The government is optimistic that ECRL operations from Gombak to the East Coast, specifically Pahang, Terengganu, and Kelantan, will be able to start in early 2027 because the construction is proceeding without hiccups and in accordance with the planned timeline.

Photo: Bernama.
The minister stated that construction in Kelantan, Terengganu, and Pahang is well underway. In Selangor, it is in its early stages, with more than 30%. However, according to the schedule, ECRL operations will begin in January 2027, and the route from Kota Bharu to LRT Gombak will be completed by the end of 2026.
-full-full_normal.jpg)
“A year later, the track from Gombak to Port Klang will be completed. Indeed, the track connecting the port in Port Klang to the East Coast is quite important because it will reach our main port for cargo transportation,” he added.
He continued by saying that cargo transportation, along with the tracks and infrastructure, is a crucial part of the ECRL because it will benefit the East Coast's industrial sector greatly, particularly Pahang.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRA1655
SELANGOR
BSQ3512
JOHOR
JYX2763
PULAU PINANG
PSC4903
PERAK
APH6581
PAHANG
CFG5949
KEDAH
KGG2081
NEGERI SEMBILAN
NEK4832
KOTA KINABALU
SJR9999*
KUCHING
QAB8364N
Last updated 26 May, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Extension from Kota Bharu to Pasir Mas Under Review
Kelantan is pushing for the ECRL to extend to Rantau Panjang, eyeing cross-border rail links with Thailand.
23-07-2025
Kuantan-Bound KL-Karak Lanes Diverted For ECRL Work Until Aug 31
Kuantan-bound lanes (KM25.75–KM26.39) are being diverted for ECRL works until Aug 31.
10-07-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Finishes Excavation Of 30 Tunnels Ahead Of Schedule
The ECRL project made three tunnel breakthroughs in a single day in the Bentong district and finished excavating 30 tunnels along its rail alignment.
14-03-2024
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
Jalan Kuala Terengganu-Kuantan Closed For ECRL Works
The Dungun district police has announced a road closure on Jalan Kuala Terengganu-Kuantan for ECRL project.
03-04-2023
Latest News
3,500+ Proton Drivers Choose ChargeSini for Home Installation, Here’s Why
Buying a Proton e.MAS? Discover why 3,500+ drivers choose ChargeSini for home EV charger installation. Get a 10% public promo!
26-05-2026
Genting "Toll" Starts May 28, But Here Is Why Malaysian Bikers Are Celebrating The New Rules
Lingkaran Cekap Sdn Bhd introduces a new RM5 road charge for cars entering Jalan Genting Highlands starting May 28, 2026, while motorcycles receive full exemption.
26-05-2026
JPJ Terengganu Calls Out Young Riders Over Alarming Rise In Riding Unlicensed & Helmetless
Terengganu JPJ Director Mohd Zamri Samion calls out the casual attitude (sikap sambil lewa) of young motorcyclists riding unlicensed and helmetless.
26-05-2026
Anthony Loke Forces Vulnerable JPJ Systems Back Online Despite Active Fraud Exposure
Transport Minister Anthony Loke instructs JPJ to postpone its online vehicle transfer system upgrade to the long weekend, keeping the system active despite major fraud warnings.
25-05-2026
The End of Crazy Price Drops: A Market Analyst Says EV Pricing Is Finally Becoming "Rational" In Malaysia
A CIMB Securities automotive analyst reveals why MITI’s new July 1 CBU EV policy will end aggressive price wars and push imported EV showroom prices past RM300k.
25-05-2026
10 BIG Reasons To Visit KLIMS 2026 Even If You’re Not A Car Enthusiast
Discover 10 massive reasons to visit KLIMS 2026 at MITEC from June 12–21, featuring free weekday entry, live RIUH concerts, a Pokémon truck, simulators, and smart transit options.
21-05-2026
Game Over, Tonto! JPJ Teams Up With MACC To Hunt Down Secret Lorry Informant Syndicates
JPJ partners with the MACC to dismantle a secret "tonto" sticker syndicate helping heavy commercial lorries evade law enforcement checkpoints.
21-05-2026
254,000 Cars Sold So Far In 2026! A Look At Which Malaysian States Are Freezing In Traffic
Over 254,000 new cars have hit Malaysian roads in the first 4 months of 2026. Discover how MAA’s April sales surged 17% as vehicle production ramped up post-Raya.
20-05-2026
Show More
trending_flat