ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion

Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak announced that the 400 KM East Coast Rail Link (ECRL) track installation from Maran, Pahang, to Kota Bharu, Kelantan, has been completed ahead of schedule by two and a half months.
For the first time in Malaysia, the CCPG-500A track-laying machine was used to lay 206 KM of tracks from Dungun, Terengganu, to Kota Bharu, Kelantan. The machine successfully completed its work at Kota Bharu Station, which will also serve as the starting point of the ECRL line.

As of Dec 2024, the ECRL project in Kelantan is 87.8% complete. This progress will help speed up the installation of electrification, signaling, and telecommunications for the remaining 43.86KM stretch in the state.
The Kelantan section includes two stations: Kota Bharu Station (for passengers) and Pasir Puteh Station (for both passengers and cargo). Both stations are expected to be completed by the second quarter of 2026.

The full 665KM ECRL line will connect Kelantan, Terengganu, and Pahang on the East Coast to Selangor on the West Coast. The project is expected to be finished by Dec 2026, with operations starting in Jan 2027. Once complete, this line is expected to boost regional economic growth and transform Malaysia’s rail network.
On ticket prices, Darwis assured that fares will be affordable, with more details to be announced by the Transport Ministry.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRN8297
SELANGOR
BST4507
JOHOR
JD6041J
PULAU PINANG
PSF3293
PERAK
APL2531
PAHANG
CFH6254
KEDAH
KGH8707
NEGERI SEMBILAN
NEL6915
KOTA KINABALU
SJT9017
KUCHING
QAB5172P
Last updated 04 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
Kids Spotted Sitting on Moving Alphard Roof in Ipoh: Police Launch Investigation Under Child Act
Ipoh police are tracking a Toyota Alphard driver after a viral video showed two kids sitting on the roof via the sunroof.
03-09-2026
"Traffic Was Slow Before The Tanker Struck": Horrific 11-Vehicle LPT1 Crash Claims 4 Lives Near Temerloh
Four people, including Kuantan’s Secangkir Cafe founders and their 4-year-old son, were killed after an out-of-control cement tanker triggered an 11-vehicle crash on LPT1 near Temerloh. Read the latest police updates.
01-09-2026
Perodua's Supplier Just Dropped A Huge RM54Mil Clue About A Secret New Model Launching In 2027
Perodua supplier MCE Holdings drops an RM54M clue about a secret 2027 model. Read about the upcoming next-gen Myvi, Bezza facelift, and local ADAS tech.
27-08-2026
Proton Almost Built A RM150,000 Mid-Engined Sports Car Using Lotus Tech & Wira Parts
Did you know Proton almost built a RM150k mid-engined sports car? Discover how 'Project Sepang' combined Lotus engineering, Wira parts, and Petronas tech.
26-08-2026
RM1,000 Trade-In Subsidy For Old Motorcycles: Transport Ministry Considers New Scheme
Got an old motor? MOT is considering a RM1,000 trade-in subsidy to help Malaysian riders upgrade to new CKD bikes. Here is how the proposed scheme works.
26-08-2026
Do You REALLY Have To Give Way To Every Siren? What Experts Say About VIP Convoys vs. Emergencies
Do you legally have to give way to VIP convoys in Malaysia? Here is what traffic laws and safety experts say about sirens, outriders, and RM10k fines.
26-08-2026
"Can I Pass My Diesel Quota To My Family?" — 3 Big Changes Coming To Malaysia’s Diesel Subsidy System
KPDN & MOF to launch 3 diesel subsidy updates in less than a month, covering family quota transfers, sambung bayar eligibility, and easier applications.
24-08-2026
Hannah Yeoh & Amirudin Shari Unveil 5 Emergency Steps To Fix Klang Valley Floods Before Budget 2027
Hannah Yeoh & Amirudin Shari unveil a 5-step Klang Valley flood mitigation plan covering dam reviews, retention ponds, and river desilting before Budget 2027.
24-08-2026
Show More
trending_flat