ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals

The East Coast Rail Link (ECRL) project is now 82.45% complete as of April 2025. The 665km railway is on track, with the Kota Bharu–Gombak stretch due by Dec 2026 and the Gombak–Port Klang section by Dec 2027.
Track installation from Maran to Kota Bharu, spanning 400 KM, finished ahead of schedule with work on the Maran–Bentong stretch beginning this month and is set to complete by June.
Electrification works started in May 2024, with over 9,000 OCS poles installed and around 2,700 left. Tunnel boring has reached 38 of 41 tunnels, with the 16.39km Genting Twin Tunnel expected to break through in Q3 this year.

Station construction is progressing well and is set for completion by mid-2026. Testing and commissioning of the system will begin in June 2026.
Transport Minister YB Anthony Loke Siew Fook shared these updates during the launch of the ECRL’s Operations & Maintenance (O&M) workforce training under the PLKI-ECRL programme.
Once operational in January 2027, the ECRL will require around 1,800 workers, with 80% being Malaysians. The aim is to build a skilled local workforce for modern rail operations.
The PLKI-ECRL programme is now focused on training for the O&M phase. A total of 3,200 trainees will benefit, starting with 210 Malaysians this year.

Of that, 102 trainees will begin one-year training in Liuzhou, China, from 15 May. They’ll learn technical and operational skills for various ECRL roles.
Trainees are guaranteed jobs upon completion and the programme is supported by a RM12 million sponsorship from China Communications Construction Company Ltd (CCCC).

ECRL will use 11 EMU train sets and 12 electric locomotives from CRRC Dalian. The first units are expected by year-end. These new trains will run up to 160 km/h, cutting travel time from Kota Bharu to Gombak to just four hours.
Loke also added that ECRL will help shift cargo from road to rail - an eco-friendly, cost-effective move in line with national transport goals.
He added that efforts are underway to ensure passenger fares remain affordable when operations begin.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRA1655
SELANGOR
BSQ3512
JOHOR
JYX2763
PULAU PINANG
PSC4903
PERAK
APH6581
PAHANG
CFG5949
KEDAH
KGG2081
NEGERI SEMBILAN
NEK4832
KOTA KINABALU
SJR9999*
KUCHING
QAB8364N
Last updated 26 May, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Kuantan Welcomes ECRL’s First Trains Ahead of 2027 Operations
The first ECRL electric passenger trains and freight locomotives have arrived in Kuantan as the project moves closer to operations in 2027.
11-02-2026
ECRL Fares To Be Announced Ahead of 2027 Launch
ECRL fares will be disclosed several months prior to the commencement of operations in January 2027, according to Transport Minister.
30-01-2026
ECRL Launch Hinges On System Integration, Jan 2027 Target Maintained
The ECRL remains on schedule, with system integration and testing now the key focus ahead of its planned Jan 2027 launch.
29-01-2026
ECRL First EMU Trains, E-Locos Head To Malaysia For Testing
Malaysia’s East Coast Rail Link gears up as its first EMUs and electric locomotives arrive for testing and future service.
17-12-2025
First ECRL Trains Depart China, Remaining Units Arriving Through 2026
First ECRL trains depart China, with remaining units scheduled to arrive through 2026.
28-11-2025
ECRL Nears Completion with 89% Progress, Operations Set for 2027
ECRL is on track to begin services from Kota Bharu to Gombak in Jan 2027, as construction progress hits 89%.
24-11-2025
ECRL Trains Fully Assembled, Ready for Malaysia
The first batch of trains for the East Coast Rail Link (ECRL) is now ready in Dalian, China.
21-11-2025
ECRL Hits 88% Milestone As Key C1B Stretch Completed
The ECRL project has hit 88% completion with the C1B Segment now successfully completed.
05-11-2025
Latest News
3,500+ Proton Drivers Choose ChargeSini for Home Installation, Here’s Why
Buying a Proton e.MAS? Discover why 3,500+ drivers choose ChargeSini for home EV charger installation. Get a 10% public promo!
26-05-2026
Genting "Toll" Starts May 28, But Here Is Why Malaysian Bikers Are Celebrating The New Rules
Lingkaran Cekap Sdn Bhd introduces a new RM5 road charge for cars entering Jalan Genting Highlands starting May 28, 2026, while motorcycles receive full exemption.
26-05-2026
JPJ Terengganu Calls Out Young Riders Over Alarming Rise In Riding Unlicensed & Helmetless
Terengganu JPJ Director Mohd Zamri Samion calls out the casual attitude (sikap sambil lewa) of young motorcyclists riding unlicensed and helmetless.
26-05-2026
Anthony Loke Forces Vulnerable JPJ Systems Back Online Despite Active Fraud Exposure
Transport Minister Anthony Loke instructs JPJ to postpone its online vehicle transfer system upgrade to the long weekend, keeping the system active despite major fraud warnings.
25-05-2026
The End of Crazy Price Drops: A Market Analyst Says EV Pricing Is Finally Becoming "Rational" In Malaysia
A CIMB Securities automotive analyst reveals why MITI’s new July 1 CBU EV policy will end aggressive price wars and push imported EV showroom prices past RM300k.
25-05-2026
10 BIG Reasons To Visit KLIMS 2026 Even If You’re Not A Car Enthusiast
Discover 10 massive reasons to visit KLIMS 2026 at MITEC from June 12–21, featuring free weekday entry, live RIUH concerts, a Pokémon truck, simulators, and smart transit options.
21-05-2026
Game Over, Tonto! JPJ Teams Up With MACC To Hunt Down Secret Lorry Informant Syndicates
JPJ partners with the MACC to dismantle a secret "tonto" sticker syndicate helping heavy commercial lorries evade law enforcement checkpoints.
21-05-2026
254,000 Cars Sold So Far In 2026! A Look At Which Malaysian States Are Freezing In Traffic
Over 254,000 new cars have hit Malaysian roads in the first 4 months of 2026. Discover how MAA’s April sales surged 17% as vehicle production ramped up post-Raya.
20-05-2026
Show More
trending_flat