ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
-full_normal.jpg)
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
The theft and vandalism cases along the East Coast Rail Link (ECRL) project continue, with the 32nd case along its alignment from Kota Bharu, Kelantan, to Port Klang, Selangor, recently recorded.
As reported by The Star, October alone saw more than nine cases take place, with the last two taking place just within 24 hours in Maran, Pahang. On Oct 10, thieves cut off a 30-metre stretch of contact wire that is part of the overhead line equipment (OHLE), thus requiring it to be replaced with a cable that is nearly a mile long.
The following day, on Oct 11, a signalling cable in a trench was cut but was not removed, where several hundred metres of cables are needed to replace them.


According to a spokesperson of China Communications Construction Company (CCC-ECRL), Shi Liang Hui, October alone saw a total of nine cases take place in various project sites, thus accumulating to 32 cases since the first one back in May this year.
The number of theft and vandalism cases for ECRL for May, June, August, Sept, and Oct are six, seven, one, nine, and nine, respectively, with no incidents in July. Going state-by-state, Pahang leads with 24 cases, followed by Terengganu at 7, and only one case has taken place in Kelantan so far this year.
Combined, these cases have led to cumulative losses amounting to around RM3 million, with all losses being borne by the contractor, at least for now.
Cable thefts and vandalism aren’t exactly a new issue in our local railway industry, as similar cases also took place in numerous railway projects, including KTM and Express Rail Link Sdn Bhd (ERL).

-full_normal.jpg)
Despite these incidents, the ECRL project is still expected to begin its commercial service in early 2027, with the whole project completion hitting 87% as of August this year.
Source: The Star
Gallery
Written By
Mukhlis Azman
An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman
JPJ Running Numbers
KUALA LUMPUR
VRU8709
SELANGOR
BSU5416
JOHOR
JG2045J
PULAU PINANG
PSG6453
PERAK
APM4216
PAHANG
CFJ1895
KEDAH
KGJ5443
NEGERI SEMBILAN
NEM3599
KOTA KINABALU
SJU6455
KUCHING
QAB7995P
Last updated 22 Oct, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
ECRL Vs Driving To Kota Bharu: Petrol, EV Or Train, Which Costs Less?
ECRL fares to Kota Bharu start at RM125. We compare train tickets with petrol and EV energy costs to see which option makes more sense.
19-10-2026
Why Extending The ECRL To Rantau Panjang Could Be A Much Bigger Deal Than It Sounds
The proposed ECRL extension to Rantau Panjang could link Malaysia with Thailand and a wider Asian rail and port network. Here's why it matters.
29-09-2026
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
Latest News
Proton's Exports Are Growing, But Not All The Cars Wear Proton Badges
Proton exported 7,370 vehicles in the first nine months of 2026, including Geely cars built in Malaysia. Here's why it matters for Tanjong Malim.
21-10-2026
6,537 Road Deaths In 2025 - Can Malaysia's New Safety Push Make A Difference?
Malaysia recorded 6,537 road deaths in 2025. With a new MOT-MIROS proposal underway, can the country meet its target to halve fatalities by 2030?
20-10-2026
ECRL Vs Driving To Kota Bharu: Petrol, EV Or Train, Which Costs Less?
ECRL fares to Kota Bharu start at RM125. We compare train tickets with petrol and EV energy costs to see which option makes more sense.
19-10-2026
"We'd Love To Go Back": Mercedes Eyes Sepang Return As F1 Night Race Idea Emerges
Mercedes-AMG Petronas F1 wants to return to Sepang, while Signify says a night race is technically possible. Could Malaysia's next F1 race be after dark?
19-10-2026
RM52,000 In Car Rebates? Sime Motors' 3-Day Sale Is Now On!
Sime Motors' 3-day sale runs from 16 to 18 October 2026 in Ara Damansara, with car rebates up to RM52,000, test drives and special offers.
16-10-2026
RM950 Million From F1 At Sepang. So Why Is Malaysia Still Hesitating?
F1 at Sepang generated nearly RM950 million in economic impact. But a five-year Malaysian GP deal could cost RM1.5 billion. Here's why.
16-10-2026
35 Cars Daily! BYD's New Miri 3S Centre Puts Aftersales In Focus
BYD's new Miri 3S Centre can service up to 35 cars daily. Here's how the latest Sarawak expansion strengthens aftersales support for EV owners.
15-10-2026
Chery Omoda 5 Recall: 600 Cars In 2024, 8,878 In 2026. What Changed?
Chery's Omoda 5 recall covers 8,878 vehicles, compared with 600 in 2024. Here's what changed, what remains unknown and what owners should do.
15-10-2026
Show More
trending_flat
Malaysia First Used Car and EV Consignment Platform
This is the best place to sell your car at true market value. Instead of accepting low dealer trade-ins, we handle everything and connect your car directly to genuine buyers for the highest price.

Understanding CariCarzAutomall Consignment Plan


Approved 200-Check Points Inspection

7 Day Money Back Guarantee

One Year Extended Warranty

No Hidden Charge