LRT3: 33 Problems Identified, Solutions Ready, Tests Ongoing
-full_normal.jpg)
Although solutions have been developed for all 33 technical issues flagged on the LRT3 Shah Alam Line, the systems have yet to complete full testing to confirm they perform reliably under operating conditions.
According to Sinar Harian, Shah Alam Line COO Mohd Ariffin Idris said the project team is now focused on extended and continuous testing, aimed at validating whether the fixes introduced truly resolve the problems encountered earlier.

He explained that while corrective measures are already in place, they must be proven through rigorous trials before the line can be considered operationally ready. Testing, he said, is still ongoing and remains a critical phase of the project.
A major area of attention is the system software, which is being upgraded to the latest baseline to ensure it can cope with both existing faults and any new issues that may emerge during testing.
Mohd Ariffin added that failure-free run (FFR) testing is currently being carried out on all trains assigned to the Shah Alam Line. A total of 22 trains must undergo the process, with each test monitored by the Land Public Transport Agency (APAD) as part of standard regulatory requirements.

Even trains that have already clocked the required mileage are not exempt, as they still need to be reassessed to ensure every technical and safety criterion is fully satisfied.
According to him, the line cannot open to passengers until all trains pass FFR testing and the entire system, including infrastructure and signalling, is confirmed to be fully complete and stable.
Testing is conducted around the clock, including overnight sessions, with specialists from original equipment manufacturers involved to address specific technical challenges. These include signalling systems supplied from Germany and rolling stock sourced from China.
He noted that uncovering new issues during dry runs is not unusual, and any problems identified will be rectified before further testing continues to ensure long-term stability.

As for the start of public operations, Mohd Ariffin said an official projection is expected to be announced by senior management around January next year, once testing reaches a more conclusive stage.
Earlier reports by Prasarana Malaysia Bhd revealed that the 33 technical issues, largely linked to software errors and system disruptions, were identified during two and a half months of testing and were a key reason behind delays to the line’s launch.
Among the problems detected were trains failing to stop precisely at platforms, issues with door operations, incorrect speed settings, failures in automatic train movement, and unintended train movement when the system should have remained static.
Written By
Kumeran Sagathevan
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well!
JPJ Running Numbers
KUALA LUMPUR
VRL1547
SELANGOR
BSS7258
JOHOR
JC4217J
PULAU PINANG
PSE6842
PERAK
APK6538
PAHANG
CFH4510
KEDAH
KGH5386
NEGERI SEMBILAN
NEL4351
KOTA KINABALU
SJT5374
KUCHING
QAB4032P
Last updated 15 Aug, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
Save RM6,000 A Year? We Calculated Your Real Savings By Switching To The New LRT3
LRT3 Shah Alam Line is now open with free rides until July 31. See how switching to public transport can save you RM6,000 annually in fuel, tolls, and parking.
29-06-2026
From 80 Sen To RM4.30: A Simple Breakdown Of The New LRT3 Fares
Planning to ride the new LRT3? Get a simple breakdown of the Shah Alam Line fares.
25-06-2026
It’s Happening! After Years Of Delays, The LRT3 Is Finally Ready To Start Operations
The long-awaited LRT3 Shah Alam Line is officially set to begin operations by the end of this month, as confirmed by Transport Minister Anthony Loke.
18-06-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
LRT3 Shah Alam Line Expected To Open In June
After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.
05-02-2026
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
Latest News
"RM100M Feels Like RM50M Now": Tun M Urges Malaysia To Buy Back Formula 1 Hosting Rights
Tun Dr Mahathir urges Malaysia to buy back Formula 1 hosting rights for Sepang, arguing RM100M is affordable today. Read his podcast comments and cost breakdown.
13-08-2026
11 Deaths In 4 Days: JPJ Introduces Mandatory Online Registration & 4-Photo Check For RXZ Members
After 11 fatal crashes during RXZ Members 8.0, JPJ mandates online registration, valid licenses, and 4 motorcycle photo uploads for future events. Read the full rules here.
13-08-2026
Leaked Sepang F1 Ticket Prices Show RM200 MyKad Rate—But There’s A Catch
Leaked F1 Sepang ticket prices show 3-day passes starting at RM200 for MyKad holders. Here is the full price breakdown and the strict verification rules you must know.
12-08-2026
Why Are NEW Kei Cars Banned From Malaysian Showrooms, But OK To Buy Used From Recon Dealers?
Ever wondered why new Kei cars aren't sold in Malaysian showrooms but thrive on recon lots? Here is how JPJ VTA rules and AP import regulations really work.
12-08-2026
32 Robots & 10-Second Color Swaps: 5 Cool Things Inside Inokom’s New RM300M Kulim Facility
Inside Inokom's new RM300M Paint Shop 3 in Kulim, Kedah: 32 robots, 10-second color swaps, 60% CO2 reduction, and a 100% Malaysian workforce.
12-08-2026
Everything You Need To Know About Kuching’s New Kia 3S Hub (Including Free Snacks & EV Readiness)
Looking for Kia in Kuching? Check out the new RM1.5M Kia 3S Centre on Jalan Abell featuring EV-ready servicing, a cozy lounge, and free snacks!
11-08-2026
Over 55k Xpander & 28k Veloz Units On Our Roads: Can Hyundai STARGAZER Steal Sales From The Japanese Kings?
With 84k Xpander and Veloz units on Malaysian roads, can the new Hyundai STARGAZER (Est. RM99k) steal sales from Japanese rivals? We analyze specs, CBU launch plans, and HMY's CKD ambitions.
11-08-2026
JPJ Inspected 12 Driving Schools In Kelantan & Issued 100 Notices For Various Offences
JPJ Kelantan audited 12 driving schools, inspecting 350 vehicles and issuing 100 notices for unsupervised 'L' drivers, missing badges, and expired road tax.
10-08-2026
Show More
trending_flat