Trans Borneo Highway’s Miri Stretch Set To Begin Construction Next Year

Anis

Share via

9194548b-pan-borneo-bernama-pic-090424.jpg Construction on the Miri stretch of the Trans Borneo Highway is finally moving forward, with the Works Ministry confirming that physical work is expected to begin in the first quarter of 2026.

Works Minister Datuk Seri Alexander Nanta Linggi told the Dewan Negara that the 4.951-kilometre section, formerly known as Miri Work Package 12 under Phase 2 of the Pan Borneo Highway (LPB2), is still in its pre-construction stage while the federal government completes the procurement and tender process.

"LPB2 has now been rebranded as two separate projects which are the Trans Borneo Highway (LTB) and the Northern Coastal Highway (NCH)," he explained.

This came in response to Senator Datuk Ahmad Ibrahim, who asked for updates on Sarawak’s LPB2 progress and how the ministry plans to avoid delays caused by contractor issues or the need for extra funding.

Pan-Borneo-Highway-from-Sarawak-to-Sabah.jpg
According to Nanta, Work Package 13 (Limbang) and Work Package 14 (Lawas) now fall under the NCH project and are being implemented by RECODA under the supervision of the Sarawak government.

As for the Pan Borneo Highway in Sarawak, Nanta reported that the 786-kilometre route has reached 99.98% progress as of Oct. 

"Ten out of eleven work packages are already completed and opened in stages to the public. The last remaining package, WPC 11, however, cannot meet its original 2025 completion timeline," Nanta added.

He said the delay stems from the urgent need to replace old water pipes belonging to Sarawak Water Sdn Bhd along the affected 4.2-kilometre stretch. The pipe replacement must be done first to prevent supply disruptions in Miri and avoid future road damage.

fmt-Pan-Borneo-Highway-bernama-21319.jpg
The Works Ministry, along with Sarawak JKR, contractors and relevant agencies, is currently renegotiating costs and scope. Pipe diversion and road upgrades are expected to roll out in phases from early 2026, with full completion targeted for the first quarter of 2029.

"Finishing WPC 11 will mark the full completion of the Pan Borneo Highway in Sarawak

"Continuous monitoring is in place to keep the projects on track and prevent delays due to contractor or funding issues," the minister assured.














Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VQT1854

SELANGOR

BSN9734

JOHOR

JYU4127

PULAU PINANG

PSB2566

PERAK

APG4843

PAHANG

CFG1471

KEDAH

KGF1826

NEGERI SEMBILAN

NEJ9761

KOTA KINABALU

SJR2757

KUCHING

QAB5238N

Last updated 11 Apr, 2026

Fuel Price

Petrol

RON 95

RM 2.59

+0.05

RON 97

RM 3.15

+0.05

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.04

+0.05

EURO 5 B7

RM 3.24

+0.05

Last updated 26 Feb, 2026

Related News

Auto News

Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.

Auto News

Land Acquisition, Utilities Relocation Delay Sabah Pan Borneo Highway

The construction of Phase 1A of the LPB is taking longer than anticipated due to difficult land acquisition and utility relocation process.

07-10-2024
Auto News

Anwar Urges State Government to Expedite Pan Borneo Highway Project in Sabah

PM Anwar states that the Sabah stretch of the Pan Borneo Highway is still lagging behind the Sarawak stretch.

Auto News

Pan Borneo Highway Project Will Be Completed This Year - Nanta

98.91% of the work on the Sarawak Pan Borneo Highway (LPB) project had been completed, says the works minister.

13-02-2024
Auto News

Works Ministry Denies Removing Barriers at Fatal Terengganu Crash Site

Works minister has refuted claims that his ministry removed the safety signs and concrete barriers at the fatal Terengganu crash site.

08-12-2025
Auto News

Works Ministry Yet To Receive Genting Road Charge Proposal

Works Ministry clarifies no formal proposal received as Genting Malaysia plans charges for road maintenance.

19-11-2025
Auto News

Genting Toll: State Leaders Seek Resident-Friendly Approach

Pahang and Bentong representatives call for reasonable rates and safeguards as Genting prepares to introduce its toll fee.

Auto News

Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

The Works Ministry is inviting proposals for an ANPR-based barrier-free MLFF toll system.

Latest News

Auto News

Why Is Global Oil Falling But Our Petrol Price Is Still High? — MOF Explains The 'Lag'

Why is global oil falling but Malaysia’s petrol price is still high? MOF explains the APM "lag effect" and why unsubsidized RON95 hit RM4.27 this week.

10-04-2026
Auto News
Auto News

SUPER GT 2026 Malaysia Might Not Happen At All? Here’s What We Know So Far

Is SUPER GT 2026 Malaysia cancelled? Reports suggest the Malaysian round may be called off due to fuel concerns and high costs. Get the latest updates here.

07-04-2026
Auto News

Is It Illegal To Borrow Your Parents' MyKad For Subsidised Petrol? Here’s What The Law Says

Can you use a family member's MyKad for Budi95 petrol? JPN warns that sharing IDs at the pump is prohibited and under investigation. Get the official rules here.

06-04-2026
Auto News

Tough Times, But Everyone Still Wants a Saga: Sales Jump 38% Despite a Slow Market

Proton Saga defies the 2026 market slump with a 38% sales surge! Discover the new 1.5L engine, Level 1 ADAS, and tech upgrades making it Malaysia’s top choice.

03-04-2026
Auto News

Malaysia Is Angry… But The World Is Already in Energy Crisis

Malaysia is cutting the BUDI95 quota to 200L. While we argue over liters, the world is in "Energy Survival Mode." Is an EV your secret to beating the 2026 crisis?

03-04-2026
Auto News

GWM Malaysia Eyes Top 10 Spot by 2028: 6 New Models to Launch, Led by Tank 300 HEV

GWM Malaysia targets Top 10 status by 2028, launching 6 new SUVs starting with the Tank 300 HEV.

02-04-2026
Auto News

Why Your Next Group Trip Costs 80% More: Diesel Hits Historic RM6.02 (April 2-8)

Malaysia's tour bus and van rates jump 80% as diesel hits a historic high.

01-04-2026

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.