"Wait, Why Is It Taking So Long?" — 4 Things Slowing Down The Pan Borneo Highway In Sabah Right Now

Pan Borneo Highway
If you’ve driven between Sandakan and Lahad Datu lately, you’ve probably spent more time looking at orange traffic cones than actual scenery.
The Pan Borneo Highway is the "dream" project we’ve been waiting for, but let’s be real, the progress bar feels like it’s stuck at 99% loading. Recently, Chief Minister Datuk Seri Hajiji Noor went down to the ground to inspect Work Package 25 (WP25), and he didn’t sugarcoat it.
The 14.96km stretch from Kampung Perpaduan Datuk Moh to Sukau is currently at 12.35% physical progress, slightly behind its 15.30% target. So, what’s the hold-up?
Here are the 4 major "speed bumps" keeping the machines from moving faster:
1. The "Invisible" Utility Maze
This is the big one. Hajiji identified utility relocation as the primary factor slowing down earthworks.
Think about it: before you can build a massive highway, you have to move miles of SESB electricity poles, water pipes, and fiber optic cables that have been there for decades. Moving these requires high-level coordination between agencies, and one wrong move could leave a whole village without water or TikTok.
2. The Logistical Tug-of-War
Moving heavy machinery through rural Sabah isn’t like driving a Myvi to the mall. The CM noted that logistical challenges are a major constraint. Getting raw materials, giant bridge beams, and specialized equipment into areas like Sukau requires precise timing and solid ground, both of which are hard to find in a construction zone.
3. "Temporary Access" Nightmares
We’ve all seen them, those narrow, bumpy diversions that keep you at a 20km/h crawl. These temporary access issues within the project area don't just annoy drivers; they actually slow down the workers too. Managing traffic while trying to build a multi-storey flyover on the same spot is basically a high-stakes game of Tetris.
4. Demolition & Land Dramas

Chief Minister of Sabah, Datuk Seri Hajiji Noor.
You can't build a road where a house is standing. Hajiji mentioned that land acquisition and the demolition of existing structures are still ongoing hurdles. Negotiating with land owners and ensuring everyone is compensated fairly takes time, and until the "site clear" signal is given, the bulldozers have to wait.
Is there light at the end of the tunnel?
Despite the delays, there is a "Save the Date" on the calendar. This RM269.9 million project is scheduled for completion by February 2028.
Once done, WP25 will feature:
- A multi-storey interchange (Flyover)
- Bus stops
- Pedestrian bridges
- Upgraded drainage to prevent those "flash flood" surprises
The government is pushing for closer coordination between agencies to stop the "blame game" and get the tarmac moving. For now, keep your snacks ready and your patience high, the road to a better Sabah is still under construction.
What do you think? Is 2028 a realistic goal or just another "Janji Manis"? Let us know in the comments!
Written By
Sofea Najmi
A Bachelor of English Language and Literature graduate with an obsession for the finer details. Sofea uses her background in translation to decode the technicalities of automotive innovation. She is dedicated to delivering impactful, meticulously researched articles that provide a narrative far beyond the spec sheet. LinkedIn: https://bit.ly/3C018vv
JPJ Running Numbers
KUALA LUMPUR
VRL1547
SELANGOR
BSS7258
JOHOR
JC4217J
PULAU PINANG
PSE6842
PERAK
APK6538
PAHANG
CFH4510
KEDAH
KGH5386
NEGERI SEMBILAN
NEL4351
KOTA KINABALU
SJT5374
KUCHING
QAB4032P
Last updated 15 Aug, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Latest News
"RM100M Feels Like RM50M Now": Tun M Urges Malaysia To Buy Back Formula 1 Hosting Rights
Tun Dr Mahathir urges Malaysia to buy back Formula 1 hosting rights for Sepang, arguing RM100M is affordable today. Read his podcast comments and cost breakdown.
13-08-2026
11 Deaths In 4 Days: JPJ Introduces Mandatory Online Registration & 4-Photo Check For RXZ Members
After 11 fatal crashes during RXZ Members 8.0, JPJ mandates online registration, valid licenses, and 4 motorcycle photo uploads for future events. Read the full rules here.
13-08-2026
Leaked Sepang F1 Ticket Prices Show RM200 MyKad Rate—But There’s A Catch
Leaked F1 Sepang ticket prices show 3-day passes starting at RM200 for MyKad holders. Here is the full price breakdown and the strict verification rules you must know.
12-08-2026
Why Are NEW Kei Cars Banned From Malaysian Showrooms, But OK To Buy Used From Recon Dealers?
Ever wondered why new Kei cars aren't sold in Malaysian showrooms but thrive on recon lots? Here is how JPJ VTA rules and AP import regulations really work.
12-08-2026
32 Robots & 10-Second Color Swaps: 5 Cool Things Inside Inokom’s New RM300M Kulim Facility
Inside Inokom's new RM300M Paint Shop 3 in Kulim, Kedah: 32 robots, 10-second color swaps, 60% CO2 reduction, and a 100% Malaysian workforce.
12-08-2026
Everything You Need To Know About Kuching’s New Kia 3S Hub (Including Free Snacks & EV Readiness)
Looking for Kia in Kuching? Check out the new RM1.5M Kia 3S Centre on Jalan Abell featuring EV-ready servicing, a cozy lounge, and free snacks!
11-08-2026
Over 55k Xpander & 28k Veloz Units On Our Roads: Can Hyundai STARGAZER Steal Sales From The Japanese Kings?
With 84k Xpander and Veloz units on Malaysian roads, can the new Hyundai STARGAZER (Est. RM99k) steal sales from Japanese rivals? We analyze specs, CBU launch plans, and HMY's CKD ambitions.
11-08-2026
JPJ Inspected 12 Driving Schools In Kelantan & Issued 100 Notices For Various Offences
JPJ Kelantan audited 12 driving schools, inspecting 350 vehicles and issuing 100 notices for unsupervised 'L' drivers, missing badges, and expired road tax.
10-08-2026
Show More
trending_flat