ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April.
The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu.
Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.
"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.
The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.
Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).
The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQT2420
SELANGOR
BSP108
JOHOR
JYU4311
PULAU PINANG
PSB2687
PERAK
APG4941
PAHANG
CFG1524
KEDAH
KGF1925
NEGERI SEMBILAN
NEJ9813
KOTA KINABALU
SJR2795
KUCHING
QAB5250N
Last updated 11 Apr, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
Latest News
Why Is Global Oil Falling But Our Petrol Price Is Still High? — MOF Explains The 'Lag'
Why is global oil falling but Malaysia’s petrol price is still high? MOF explains the APM "lag effect" and why unsubsidized RON95 hit RM4.27 this week.
10-04-2026
Proton X50 ‘Black Edition' Look Goes Permanent: Quartz Black Now Available for All Variants
Proton X50 Quartz Black is now permanent for all variants!
09-04-2026
SUPER GT 2026 Malaysia Might Not Happen At All? Here’s What We Know So Far
Is SUPER GT 2026 Malaysia cancelled? Reports suggest the Malaysian round may be called off due to fuel concerns and high costs. Get the latest updates here.
07-04-2026
Is It Illegal To Borrow Your Parents' MyKad For Subsidised Petrol? Here’s What The Law Says
Can you use a family member's MyKad for Budi95 petrol? JPN warns that sharing IDs at the pump is prohibited and under investigation. Get the official rules here.
06-04-2026
Tough Times, But Everyone Still Wants a Saga: Sales Jump 38% Despite a Slow Market
Proton Saga defies the 2026 market slump with a 38% sales surge! Discover the new 1.5L engine, Level 1 ADAS, and tech upgrades making it Malaysia’s top choice.
03-04-2026
Malaysia Is Angry… But The World Is Already in Energy Crisis
Malaysia is cutting the BUDI95 quota to 200L. While we argue over liters, the world is in "Energy Survival Mode." Is an EV your secret to beating the 2026 crisis?
03-04-2026
GWM Malaysia Eyes Top 10 Spot by 2028: 6 New Models to Launch, Led by Tank 300 HEV
GWM Malaysia targets Top 10 status by 2028, launching 6 new SUVs starting with the Tank 300 HEV.
02-04-2026
Why Your Next Group Trip Costs 80% More: Diesel Hits Historic RM6.02 (April 2-8)
Malaysia's tour bus and van rates jump 80% as diesel hits a historic high.
01-04-2026
Show More
trending_flat