ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April.
The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu.
Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.
"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.
The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.
Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).
The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.
Gallery
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRF6081
SELANGOR
BSR5144
JOHOR
J9999J*
PULAU PINANG
PSD6847
PERAK
APJ7414
PAHANG
CFH1307
KEDAH
KGG9647
NEGERI SEMBILAN
NEK8743
KOTA KINABALU
SJS9915
KUCHING
QAB1767P
Last updated 11 Jul, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
Latest News
No Helmet, No Exceptions: JPJ Confirms Summonses For Viral Campaign Convoy Riders
JPJ confirms summonses for helmetless riders in viral campaign convoys. Minister Anthony Loke emphasizes that safety laws apply to everyone, regardless
10-07-2026
No License, No Insurance, And Ketum: The Reality Behind JPJ’s Roadblock Crackdown
Over 91,000 vehicles inspected. More than 42,000 notices issued. These aren't just figures on a report, they represent a massive, ongoing shift in how authorities are policing our roads.
10-07-2026
Hybrid, Petrol, Or EV? Toyota’s Latest Sales Figures Prove Malaysians Love Having Options
UMW Toyota reports 36,200 units sold in 1H 2026. Discover how Toyota's "Multi-Pathway" strategy—from petrol and hybrids to EVs—is winning over Malaysian drivers.
10-07-2026
PSA: If You Don't Fix Your Chevy Airbag By 2026, Your Next Service Trip Is To Thailand
Your free window is closing. If you drive a used Chevrolet Cruze, Sonic, Trax, or Orlando in Malaysia, your factory airbag support expires in December 2026. Here is why you might have to drive to Thailand if you keep procrastinating.
08-07-2026
More Than A Service Centre? This New OMODA | JAECOO Outlet In Selayang Has A Coffee Lounge & Free Wi-Fi
Servicing your car shouldn't be a chore. Check out the new OMODA | JAECOO Selayang 3S centre, featuring a modern coffee lounge, free Wi-Fi, and top-tier service.
07-07-2026
This Lucky UiTM Student Is Driving Home A Brand New Perodua Myvi After Downloading P-Circle App
A 22-year-old UiTM student just scored a brand-new Perodua Myvi after downloading the P-Circle super app! Find out how she won the KLIMS 2026 grand prize.
07-07-2026
Netizens Are Calling PMX A Hypocrite For Riding A Bulletproof BMW 7 Series—But Here’s The Plot Twist
Netizens are calling PMX a hypocrite over a bulletproof BMW 7 Series. But here is the massive government plot twist behind the armored vault on wheels.
07-07-2026
RM8,000 To RM34,000 Off: Which Honda Deal Is Actually Worth Your Money?
Honda Malaysia’s July 2026 promo offers up to RM34,000 off! From the e:N1 EV to HR-V and Civic RS mystery rebates, here is our ultimate buyer's guide.
07-07-2026
Show More
trending_flat