ENZHMS
Link Copiedcheck_circle
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

Anis

Share via




The East Coast Rail Link (ECRL) project's Kuantan Tunnel, which broke ground in October last year, will be completed by the end of April. The 2.8km tunnel located in Jabor, near here, is the longest among the ECRL tunnels in Section B (Dungun-Mentakab), which also includes the 1.1km Paka Tunnel and 871m Dungun Tunnel, both in Terengganu. Wan Kamal Wan Embong, regional construction manager (Section 4 and 5) for Malaysian Rail Link (MRL), stated that the Kuantan Tunnel breakthrough occurred on October 17, last year, two months ahead of schedule.


"The tunnel's completion date is set for April 27. The Kuantan Tunnel runs through both Pahang and Terengganu, with 976 metres in Pahang and the remaining 1,890 metres in Terengganu "he told reporters yesterday during a media visit to the Kuantan Tunnel here. The New Austrian Tunnelling Method (NATM), the world's most widely used underground construction method, is being used in the drilling and blasting work for the Kuantan tunnel project, which began on October 7, 2019. The average height and width of the Kuantan Tunnel are 11.89m and 13.26m, respectively.



The project made use of a Swedish-made double-arm jumbo drilling machine, with tunnelling work beginning in both directions and meeting in the middle. Wan Kamal stated that MRL ensured that all workers strictly adhered to the safety aspects and conditions set by the Department of Occupational Safety and Health (DOSH). "Because tunnel construction required working in a confined space, we had to ensure proper ventilation and control gas emissions inside the tunnel that could endanger the workers. At the peak of the project, 177 workers were on the job "he said, adding that safety was given top priority during the blasting operations.


Closed-circuit television cameras were previously reported to have been installed at the construction site, including inside the tunnel, to monitor worker movement and ensure safety. In terms of the overall progress of the ECRL, Wan Kamal stated that the 665km rail project was 40% completed and was on track to be completed in December 2026. The 210km Dungun-Mentakab main line is also known as Section B, while the other sections are Kota Baru to Dungun (Section A) and Mentakab to Port Klang (Section B) (Section C).


The ECRL, which opened in 2017, will connect the east coast states of Kelantan, Terengganu, and Pahang with the Klang Valley.

Gallery

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VQT5654

SELANGOR

BSP1578

JOHOR

JYU6073

PULAU PINANG

PSB3574

PERAK

APG5721

PAHANG

CFG1837

KEDAH

KGF2754

NEGERI SEMBILAN

NEK941

KOTA KINABALU

SJR3395

KUCHING

QAB5401N

Last updated 16 Apr, 2026

Fuel Price

Petrol

RON 95

RM 2.59

+0.05

RON 97

RM 3.15

+0.05

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.04

+0.05

EURO 5 B7

RM 3.24

+0.05

Last updated 26 Feb, 2026

Related News

Auto News

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023

Latest News

Auto News

B10 to B15: What the Biodiesel Shift Means for Your 4x4 Maintenance

Malaysia shifts to a B15 biodiesel mandate. Learn what this means for your 4x4 engine, maintenance costs, and why the government is making the move.

15-04-2026
Auto News

Proton Makes History: Malaysia’s First Passenger Car Maker to Secure ISO 50001 Certification

PROTON makes history as Malaysia's first passenger car manufacturer to achieve ISO 50001: 2018 certification. Learn how energy efficiency is powering PROTON's future.

15-04-2026
Auto News

15,370 Units & Counting: How Toyota is Outrunning the 'New Brand' Invasion in 2026

UMW Toyota Motor hits 15,370 units in Q1 2026. Discover how the 'Extra Mile' strategy and new hybrid Harrier are helping Toyota outrun new market rivals.

14-04-2026
Auto News

Stable for Now, Critical by June: A Survival Guide to Malaysia's Mid-Year Energy Uncertainty

Malaysia’s fuel supply is "stable for now," but June is critical. Learn how the new diesel purchase limits in Sabah & Sarawak affect your travel and why T20 drivers should watch for RON 95 targeted subsidy announcements this year.

14-04-2026
Auto News

The End of RM1.99? World Bank Urges RM2.05 Price Tweak

The World Bank urges Malaysia to raise RON95 petrol prices to RM2.05. With a RM4 billion monthly subsidy bill and Brent crude at US$100, find out why the RM1.99 era might be ending.

13-04-2026
Auto News

From Wok to Work: FELDA’s B100 Biodiesel Can Fix the Diesel Price Crisis?

FELDA Chairman Ahmad Shabery Cheek reveals how B100 Biodiesel (Palm Oil) could fix Malaysia's diesel price crisis. Learn about the RM4.50 price target and the 50,000km engine trials.

13-04-2026
Auto News

A Sense of Crisis: What Toyota, Ford, and Honda’s Leadership are Saying About the Future

Legacy automakers are facing a 'Change or Die' moment. From Honda's $15.8 billion loss to Toyota's survival warning, see why 'China Speed' is winning.

11-04-2026
Auto News

Why Is Global Oil Falling But Our Petrol Price Is Still High? — MOF Explains The 'Lag'

Why is global oil falling but Malaysia’s petrol price is still high? MOF explains the APM "lag effect" and why unsubsidized RON95 hit RM4.27 this week.

10-04-2026

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2026 CariCarz.com. All Rights Reserved.